Mumbai/Project record

MahaRERA · the public record

THE GREEN CREST

TALOJA · SAI SHRADHA DEVELOPER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000021830

Delivery and registration

When is the project declared for completion?

THE GREEN CREST is registered with MahaRERA as P52000021830 and the promoter has declared completion for 29 Mar 2025.

29 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000021830
Registered on31 Jul 2019
Promoter-declared completion29 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THE GREEN CREST record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Shradha Developer is the promoter of record on 19 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

19projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THE GREEN CREST in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
WING B1G+731 Mar 2023
WING C1G+431 Mar 2023
WING A1G+831 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Mar 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reas

Location, Land & Connectivity

Located at TALOJA, TALOJA MAJKUR, Panvel, Raigarh, 410208. Per the filed land record, the plot is bounded to the north by 3, to the south by 2, to the east by GAVTHAN and to the west by 8B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park21 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport25 km
Andheri MIDC / SEEPZ25 km
Lower Parel / Worli business district30 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Shradha Developer is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Shradha Developer

SAI Shradha Developer
FlaggedRaigarh

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited

Other RERA-registered projects in Raigarh

The Green Crest Phase II
possession by Dec 2029 · SAI Shradha Developer
THE Green Orchid Phase III
possession by Dec 2026 · Shakti Developers
The Highlands, Godrej City, Panvel
possession by Sep 2026 · Caroa Properties LLP
THE IVY
possession by Dec 2026 · Estrela Estates
THE Jewel
possession by Dec 2029 · Kohinoor Developers
THE Landmark
declared completion Jun 2026 · Shekhar Vasant Dhumal & Three Others

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026