MahaRERA · the public record
The Icon Phase 1
Dhokali · Leading Frontier Private Limited
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Dec 2023
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51700018370
Delivery and registration
When is the project declared for completion?
The Icon Phase 1 is registered with MahaRERA as P51700018370 and the promoter has declared completion for 30 Dec 2023.
30 Dec 2023
declared completion
33months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51700018370 |
| Registered on | 26 Oct 2018 |
| Promoter-declared completion | 30 Dec 2023 |
| Current status | Certificate Signed |
| Against today | about 33 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for The Icon Phase 1 record 21 quarterly progress reports since registration.
21quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Leading Frontier is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
5projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for The Icon Phase 1 in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+32.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| B1 Madison 1 | 1 | G+28 | - |
| A2 Madison 2 | 1 | G+32 | - |
Legal and disputes
What disputes are disclosed?
8 complaints are on the MahaRERA record for The Icon Phase 1, with orders passed in 7 of them.
8complaints
7with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000195246 | 14/12/2020 | Nilesh Prabhakar Dhage vs Leading Frontier Pvt Ltd | order passed |
| CC006000000500491 | 05/07/2024 | Raj Meshram vs 1)CHEN ZHENGXING 2) Darshan Maru 3) Peng Qing 4) Li Jian 5) Yiteng Hung 6) Ankita Bafna | order passed |
| CC006000000408094 | 07/11/2023 | Prasad Jayakar Shetty vs Leading Frontier pvt Ltd | order passed |
| CC12400917 | 28/11/2024 | Aldrich Dantas vs Leading Frontier Private Limited | order passed |
| CC12500350 | 31/01/2025 | Anushree Nair Ravindran Nair vs Leading Frontier Private Limited | pending / no order on file |
| CC12501077 | 31/03/2025 | priya dinesh navalkar vs Leading Frontier Private Limited | order passed |
| CC12501274 | 16/04/2025 | Rajashree Hambir vs Leading Frontier Private Limited | order passed |
| CC12504045 | 17/11/2025 | Leading Frontier Private Limited vs Manisha Sudhir Suryavanshi and Sudhir N Suryavanshi | order passed |
Legal & Litigation
The promoter has declared 8 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | Writ Petion No 1868 | 2016 | At Admission Stage Next Date Second July Two Thousand Nineteen |
| Thane Civil Court | Civil Suit no 791/2010 | 2010 | Matter Is For Evidence Of Defendants Are Ongoing Next Date Eight March Two Thousand Nineteen |
| Bombay High Court | Writ Petition No 8395 of 2015 I to R | 2015 | At Admission Stage Next Date Twelth July Two Thousand Nineteen |
| Thane Civil Court | Civil Suit No 426/2017 | 2017 | Stage Of Matter Was For Written Statement And Reply Of The Defendants Next Date Sixteenth March Two |
| Thane Civil Court | Thane Court, R C A 65/2017 | 2017 | Bombay High Court F Y Five Hundred Tow By Two Thousand One Is Disposed And Trfd To Thane High Court |
| Bombay High Court | Writ Petition No 7204 of 2016 | 2016 | Dose Not Pertains To Land But Pertain To D P Road Now At Admission Stage Next Date Eleventh March T |
| Before Sub Divisional Officer Thane | Before SDO Officer Thane Appeal no 202/2018 in Tahasildar Thane 84 CC proceeding no 87/2017 | 2018 | Tenancy Appeal Against Order Dated Eighteenth July Two Thousand Eighteen Passed In Tahasildar Thane |
| High Court Bombay | Civil Writ Petition L No 35982/2018 | 2018 | Writ Petition Is Filed For Quashing The Proceedings Filed Before The Sun Divisional Office Thane Bea |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2023 | Impact of COVID 19 is severe more particularly on Real Estate Sector. The major impacts are narrated as under :- 1. Set-back of Migrated Workers resulting in non availability of |
Location, Land & Connectivity
Located at Dhokali, Highlands Garden Road, Thane, Thane, 400608. Per the filed land record, the plot is bounded to the north by University of Mumbai Thane Sub Centre, to the south by 20 M W DP Road, to the east by Runwal Garden City and to the west by 25 M W DP Road. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 14 km |
| Andheri MIDC / SEEPZ | 16 km |
| Chhatrapati Shivaji Int'l Airport | 20 km |
| Bandra Kurla Complex (BKC) | 21 km |
| Lower Parel / Worli business district | 30 km |
| Nariman Point / Fort | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.