Paramount D

Balkum · Kalpataru Homes Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700021474

Delivery and registration

When is the project declared for completion?

Paramount D is registered with MahaRERA as P51700021474 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700021474
Registered on05 Jul 2019
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Paramount D record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Kalpataru Homes is the promoter of record on 53 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

53projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Paramount D, ₹80.18 Cr of a declared ₹87.56 Cr estimated project cost is reported as incurred, about 91.6%, as at the last certified filing with MahaRERA.

91.6%

₹80.18 Cr

of ₹87.56 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Paramount D in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+39.

BuildingWingsFloorsDeclared completion
Tower 4 - Camellia1G+3931 Dec 2023

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Paramount D, with orders passed in 2 of them.

3complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000059144506/08/2024Devkinandan Manguram Pujari vs Kalpataru Homes Private Limitedorder passed
CC1240069207/11/2024Bhushan Prataprao Pawar vs Kalpataru Homes Private Limitedorder passed
CC1260117703/03/2026Devkinandan Manguram Pujari vs Kalpataru Homes Private Limitedpending / no order on file

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 4 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court9712005Pending
Additional Collector Appeal Thane102012Pending
Bombay High Court49772018Pending
Bombay High Court134512018Pending

Location, Land & Connectivity

Located at Balkum, Bhiwandi Road , Andheri, Mumbai Suburban, 400608. Per the filed land record, the plot is bounded to the north by S No 115-14 pt 115-10-2 pt of village majiwade, to the south by SNo115-14ptMajiwade n SNo212-2A pt 213-1A ofbalkum, to the east by SNo 115-15pt 115-14 pt 115-10-2 pt of majiwade and to the west by SNo 115-14pt of majiwade and SNo 212-2A of balkum. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~154 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park154 km
Andheri MIDC / SEEPZ155 km
Chhatrapati Shivaji Int'l Airport159 km
Bandra Kurla Complex (BKC)161 km
Lower Parel / Worli business district169 km
Nariman Point / Fort176 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kalpataru Homes Private Limited is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Balkum

Dosti West County - Dosti Tulip
possession by Oct 2026 · Dosti Enterprises
Highland Springs B4 D Wing
possession by Dec 2026 · Siddhi Real Estate Developers
Mahavir Bliss
possession by Dec 2026 · M/s. Shivshakti Engineers
Shraddha Peninsula
possession by Dec 2026 · Padmagriha Heights
Sumeet Elite
possession by May 2027 · Vedant Construction
Dosti West County - Dosti Nest - Phase 1
possession by Jun 2027 · Dosti Enterprises

Major developers building in Balkum

Other RERA-registered projects in Thane

Paras Apartment CO-OP. Housing Society LTD
possession by Jun 2027 · Shiv Infra
Parasmani Park CHS
declared completion Jan 2024 · Sandeep Daji Lakade
Pardeshi Empire
declared completion Mar 2025 · Vishnu Developers
Pardeshi Paradise
declared completion Jul 2023 · Vishnu Developers
Parijas Horizon
possession by Jun 2028 · Octave Infraventures LLP
Parijatak Phase I A AND B Wing
declared completion Jun 2026 · Varad Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026