MahaRERA Property Intelligence · Thane

THE SIGNATURE

P51700018837 · GANPATI MANDIR ROAD · promoter Impressions Buildcon

Certificate SignedDue 29 Feb 2024

Delivery & Registration

MahaRERA registrationP51700018837
Registered on06 Dec 2018
Promoter-declared completion29 Feb 2024
Current statusCertificate Signed
Against todayabout 29 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Impressions Buildcon is the promoter of record on 17 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹8.56 Cr spent against a ₹8.56 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 25 homes filed with MahaRERA, 21 are sold/booked and 4 remain available (~84% sold) — selling steadily. Buyers have committed ₹24.18 Cr in agreement value so far. Of that, ₹20.20 Cr (~84%) is already collected, ₹15.93 Lakh receivable — a read on how far along these sales really are. Note: the project registers 32 homes in total, but this sold/unsold inventory filing covers only 25 of them — the other 7 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 21 registered agreements, the effective carpet rate is ₹13,175/sqft (typical range ₹7,763–₹21,795) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 10FLAT NO 1002658 sqft (61.09 sqm)₹44.71 Lakh
Floor 4FLAT NO 404400 sqft (37.19 sqm)₹27.22 Lakh
Floor 8FLAT NO 802658 sqft (61.09 sqm)₹44.71 Lakh
Ground/Floor 0OFFICE165 sqft (15.33 sqm)₹11.22 Lakh

⚠ The inventory filing also declares: 7 owner/investor-held. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11 and 32 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
THE SIGNATURE1G+113231 May 2022

Unit mix on the filing: 18 residential and 14 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 May 202329 Feb 2024MATERIAL AND LABOUR SHORTAGE AND PANDEMIC SITUATION GAP

Location, Land & Connectivity

Located at GANPATI MANDIR ROAD, APTE WADA GANPATI MANDIR ROAD DOMBIVLI EAST 421201, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by CHEDDA ROAD, to the south by JANKI HARI CO OP SOCIETY, to the east by GANPATI MANDIR ROAD and to the west by LAXMI BAUG ESTATE CO OP SOCIETY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~23 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park23 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport28 km
Bandra Kurla Complex (BKC)29 km
Lower Parel / Worli business district37 km
Nariman Point / Fort43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Premsadan CHS
possession by Jul 2026 · Namrata Realtors
OM Trimurti Darshan
possession by Aug 2026 · Prachi Group
Pannash
possession by Aug 2026 · Technicon
Rashmi Priya CO-OP HSG SOC LTD
possession by Aug 2026 · Shree Riddhi Siddhi Infraproject
Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel

Major developers building in Dombivli East

Other RERA-registered projects in Thane

THE Signature
possession by Mar 2027 · Rajesh Yadav
THE Trellis
possession by Mar 2029 · Maithili Builders Private Limited
The Universe II
declared completion Dec 2023 · G.e.constructions
The Universe - Mercury
declared completion Dec 2023 · G.e.constructions
The Universe Neptune - B
declared completion Jun 2024 · Gayasuddin Riyazuddin Khan
THE Vaidiki Aarambh
possession by Dec 2030 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026