TRAFALGAR TOWER

P51800006369 · promoter Akshay Radha Kishan

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51800006369
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Akshay Radha Kishan is the promoter of record on 74 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+37.

BuildingWingsFloorsDeclared completion
TRAFALGAR TOWER1G+3730 Jun 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Jun 2022The project got delayed due to COVID 19 pandemic. Moreover, as per DCR 2034 we are entitled to additional FSI of 0.54 beyond the above stated 2.70 FSI the abutting R.B. Mehta road
30 Dec 202230 Dec 2020we are unable to obtain approvals for the next set of amended plans for a 15 floor building since there still is no clarity on the 33 7(B) Rule of DCR 2034. We have been waiting

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400077. Per the filed land record, the plot is bounded to the north by GOKUL BUILDING, to the south by VRINDAVAN BUILDING, to the east by R B MEHTA MARG and to the west by MUNICIPAL SCHOOL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park5 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Baldevsingh Thakur SRA Coop HSG SOC LTD
possession by Jul 2026 · Krishna Narsingrao Pimple
Palatina
possession by Jul 2026 · Tanishq Builders
Vihar Heights
possession by Aug 2026 · Saptrishi Homes LLP
Poonam Celeste
possession by Aug 2026 · PL7 Realty Pvt. Ltd.
Hema Apartments CO-Operative Housing Society Limited
possession by Sep 2026 · Hema Appartments CO-Operative Housing So
Centrona ZEN-A
possession by Dec 2026 · Elevated Avenue Realty LLP

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai Suburban

Transcon Fortune 500 Tower 1
possession by Dec 2026 · Samta Builders Pvt. Ltd.
Transcon Ramdev Plaza
possession by Dec 2026 · Transcon Iconica Private Limited
Transcon Triumph Tower 1
declared completion Dec 2022 · Transcon Developers Pvt. Ltd.
Transcon Triumph Tower 2
declared completion Jun 2026 · Transcon Triumph Phase 2 Private Limited
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
Transcon Triumph Tower 4
possession by Mar 2027 · Transcon Triumph Phase 2 Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026