TRINITY OASIS

Majiwade · ANIL thakurdas kursija

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008216

Delivery and registration

When is the project declared for completion?

TRINITY OASIS is registered with MahaRERA as P51700008216 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008216
Registered on18 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TRINITY OASIS record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Anil Thakurdas Kursija is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for TRINITY OASIS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
Trinity Oasis- S41G+2031 Jul 2022

Legal and disputes

What disputes are disclosed?

13 complaints are on the MahaRERA record for TRINITY OASIS, with orders passed in 13 of them.

13complaints

13with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001271916/02/2018GORDEN JAGWANI vs BALAJI CONSTRUCTION COMPANYorder passed
CC00600000002334016/02/2018RAMESH HOTCHAND PREMANEY vs BALAJI CONSTRUCTION COMPANYorder passed
CC00600000000172508/11/2017M Sadanandam Mukkamala vs Anil Kursijaorder passed
CC00600000002340921/02/2018HARISH AWTANEY vs ANIL THAKURDAS KURSIJAorder passed
CC00600000002375216/03/2018Chander Tejwani vs Anil Kursijaorder passed
CC00600000004423524/04/2018Suresh Varlani vs Anil Kursijaorder passed
CC00600000019227122/01/2020Komal S Khilnani vs Balaji Construction Companyorder passed
CC00600000005540716/07/2018Rajesh Singh vs Balaji Construction Companyorder passed
CC00600000005564711/08/2018Ashutosh Ashok Lokhande vs M/s. Balaji Associates, Thro' Mr. Anil Thakurdas Kursijaorder passed
CC00600000005644104/10/2018Vidya Bhushan Prasad vs Balaji Construction Companyorder passed
CC00600000005795406/02/2019MAHADEVAN JAYRAM AYER vs balaji construction companyorder passed
CC00600000025158424/06/2022Kishore Amrutlal Harsora vs Balaji Construction Coorder passed
CC1250436009/12/2025Vidya Bhushan Prasad vs Trinity Oasis Cooperative Housing Society Limitedorder passed

Location, Land & Connectivity

Located at Majiwade, Thane, Thane, 400610. Per the filed land record, the plot is bounded to the north by S NO 100, to the south by 30 M DP ROAD, to the east by 60 M DP ROAD and to the west by S NO 100. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park13 km
Andheri MIDC / SEEPZ14 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anil Thakurdas Kursija is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Anil Thakurdas Kursija

Anil Thakurdas Kursija
FlaggedThane

Other RERA-registered projects in Majiwade

Infinity Towers
possession by Dec 2026 · T Bhimjyani Realty Pvt.ltd.
Raunak Imperial
possession by Dec 2026 · Raunak Avenue Realty
ZEN
possession by Dec 2026 · Neelkanth Realtors PVT LTD
Serein Phase II
possession by May 2027 · Ardent Properties Private Limited
Mahavir Spring -Daffodils-P3
possession by Dec 2027 · Vinayak Developers
Courtyard - Asteria A
possession by Dec 2027 · Courtyard Real Estate Private Limited

Major developers building in Majiwade

Other RERA-registered projects in Thane

Trinity Oasis Phase II
declared completion Dec 2024 · Anil Thakurdas Kursija
Trinity Paradise Phase 1
declared completion Mar 2026 · Trinity Builders
Trinity Phase 2
possession by Mar 2030 · Trinity Builders
Trinity - Shashank Saptshrung
possession by Aug 2028 · Radhika Construction Company
Trishan Enclave
possession by Dec 2028 · Omkar Enterprises
Trishul Goldfield
possession by Jun 2027 · Patel & Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026