TRULIFE

KARJAT · HNH-HD JV

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

19units filed as unsoldInventory · 19 September 2026
31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000047832

Delivery and registration

When is the project declared for completion?

TRULIFE is registered with MahaRERA as P52000047832 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000047832
Registered on28 Nov 2022
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for TRULIFE record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In TRULIFE, 69 of 132 plots filed with MahaRERA are recorded as sold or booked, about 52%, and 61 remain available.

52%sold

69 of 132 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What the filings record, plot by plot

Read from MahaRERA on 19 September 2026

MahaRERA publishes, plot by plot, what this promoter filed: which plots are sold and which are not, the filed area of each, and for the sold ones the registered agreement value — the consideration filed for that specific plot. On this project 72 plots carry one, and 19 of the 102 are recorded unsold. Since we started watching this ledger, 13 plots have moved out of the unsold list, most recently on 19 September 2026.

Here is one of those unsold plots, priced against what buyers of comparable plots on the same filing actually filed:

PlotAreaFiled for comparable plots on the same filingBased on
1161,615 sqftRs 13.19 lakh typical, over Rs 8.88 lakh to Rs 17.92 lakh32 filed at this size

A filed consideration is what was registered for one plot. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the plot is available to you today.

In TRULIFE, every one of the 19 unsold plots has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 18 plots — ₹2,999 →

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2027The said project is villa plotting project which is near the valley area, and due to water lagging and technical issues. The project is delayed to complete the site work. So requir

Location, Land & Connectivity

Located at KARJAT, KHANDAS MURBAD ROAD, Thane, Thane, 410201. Per the filed land record, the plot is bounded to the north by SURVEY NO 13-2, to the south by KHANDAS MURBAD ROAD, to the east by SURVEY NO 13-14 and to the west by SURVEY NO 11. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~57 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park57 km
Bandra Kurla Complex (BKC)61 km
Andheri MIDC / SEEPZ61 km
Chhatrapati Shivaji Int'l Airport61 km
Lower Parel / Worli business district65 km
Nariman Point / Fort68 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Tukaram Palace
declared completion Mar 2023 · Premji Dosha Vaviya
Tulip
possession by Dec 2026 · Walmik Raghunath Khairnar
Tulip
declared completion Jun 2023 · Living Stone Developers
Tulip Apartment
declared completion Dec 2019 · Mukesh Shrinath Sharma
Tulip Kingdom
possession by Dec 2028 · Shivam Enterprises Proprietor Prakash M
Tulip Palace
possession by Dec 2026 · Wings Buildcon

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026