MahaRERA Property Intelligence · Mumbai Suburban

Udyam Kunj CHS Redevelopment Phase I

P51800009775 · Opp Navjivan High School · promoter Mahendra Bhaskar Mhatre

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800009775
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mahendra Bhaskar Mhatre is the promoter of record on 68 projects, of which 13 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
Udyam Kunj1G+9-

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002288416/01/2018Jyotsna Narendra Kesarkar vs Mahendra Bhaskar Mhatreorder passed
CC00600000007915404/05/2019HARSHAD GANPATRAO SURVE vs MAHENDRA BHASKAR MHATREorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay HighcourtS/314/20152015Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Dec 2018Due to issue of exorbitant Assessment charges notice issued by MCGM so negotiation with M.C.G.M. is in process to mitigate the Assessment Charges of 48,00,000.00.

Location, Land & Connectivity

Located at Opp Navjivan High School, Rani Sati Marg, Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by Private Passage of Bhalchandra N Gokhale, to the south by 12 20 Meter wide D P Road, to the east by Property of Bhalchandra N Gokhale and to the west by Bungalow known as Mangalam. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport10 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad East

DEM Phoenix
possession by Jul 2026 · DEM Buildwell
Rajhans Solitaire
possession by Aug 2026 · Rajhans Residency
Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd

Other RERA-registered projects in Mumbai Suburban

Udyanjali Chs
declared completion Dec 2020 · Ashray Developers
Ugam
declared completion Jun 2024 · Gurukrupa Realcon Developers Private Lim
Ujval
declared completion Sep 2022 · Paranjape Schemes LTD
UK Iona A - B Wing
possession by Dec 2026 · Keemaya Build Private Limited
UK Iona C Wing
possession by Dec 2027 · Keemaya Build Private Limited
UK Iridium
declared completion Oct 2024 · Damodar Suruchi Developers Pvt. Ltd.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026