MahaRERA Property Intelligence · Thane

VAISHNAVI PRIDE

P51700045901 · Kalyan East · promoter Ashtavinayak Enterprises

Certificate SignedDue 30 Apr 2027

Delivery & Registration

MahaRERA registrationP51700045901
Registered on15 Jun 2022
Promoter-declared completion30 Apr 2027
Current statusCertificate Signed
Against today9 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ashtavinayak Enterprises is the promoter of record on 60 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~28.7% of the estimated project cost incurred as of the last certificate (₹20.52 Cr spent against a ₹71.56 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. With only ~9 months to the declared date and ~28.7% of the cost incurred, ask the promoter how the balance gets built in the time left.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
VASIHNAVI PRIDE1G+12-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Kalyan East, Tisgaon, Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by ROAD, to the south by SURVEY NO 69A, to the east by HAJI MALANG ROAD and to the west by LAND PROPERTY OF JAMADAR WOODEN WORKS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ashtavinayak Enterprises is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Ashtavinayak Enterprises project & its RERA track record →

Other flagged projects by Ashtavinayak Enterprises

Ashtavinayak Enterprises
FlaggedRaigarh
Ashtavinayak Enterprises
FlaggedThane
Ashtavinayak Enterprises
FlaggedThane
Ashtavinayak Enterprises
FlaggedThane

Other RERA-registered projects in Kalyan East

Krishna Square
possession by Jul 2026 · Gopal Krishna Developers
SAI Heights
possession by Aug 2026 · Aaradhana Construction
Avighna Karan Wing C
possession by Aug 2026 · Avighna Karan
Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Durga Imperial
possession by Oct 2026 · G K Mali & C K Mali

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Vaishnavi Pride
possession by Dec 2026 · Vaishnavi Developers
Vaishnavi Villa
declared completion Aug 2023 · Srushti Enterprises AND Rohini Enterpris
Vakratund
declared completion Jul 2018 · Shree Siddhi Vinayak Developers
Vakratunda Anantaraa Business Park
possession by Oct 2030 · Ispl Machine Builders Limited
Vakratunda Anantaraa Tower 1
possession by Apr 2032 · Ispl Machine Builders Limited
Vakratunda CHS
declared completion Dec 2025 · Arya Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026