Mumbai/Project record

MahaRERA · the public record

VARDHMAN HEIGHTS

BANDREKAR WADI, JOGESHWARI EAST · VARDHMAN INFRASTRUCTURES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800019367

Delivery and registration

When is the project declared for completion?

VARDHMAN HEIGHTS is registered with MahaRERA as P51800019367 and the promoter has declared completion for 31 Mar 2022.

31 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800019367
Registered on23 Jan 2019
Promoter-declared completion31 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARDHMAN HEIGHTS record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vardhman Infrastructures is the promoter of record on 29 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

29projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VARDHMAN HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
VARDHMAN HEIGHTS1G+1831 Mar 2020

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for VARDHMAN HEIGHTS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000014108301/10/2019manoj mangilal kothari vs Vardhman Infrastructutreorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2022DUE TO COVID PANDEMIC

Location, Land & Connectivity

Located at BANDREKAR WADI, JOGESHWARI EAST, NILESH SAWANT MARG, Borivali, Mumbai Suburban, 400060. Per the filed land record, the plot is bounded to the north by RAMJI PATEL CHAWL, to the south by OM PRAKASH CHAWL, to the east by ROAD and to the west by BABA SINGH CHAWL. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari East

Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises
Avant Heritage - III
possession by Dec 2026 · Avant Heritage III Realty Pvt. Ltd.
Devbhoomi
possession by Dec 2026 · Metro Capital
Iifl Centre
Developer in insolvency (NCLT) · possession by Dec 2026 · Spenta Sun City Private Limited

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

Vardhman Springs
possession by Dec 2028 · Vardhman Developers LTD
Varella Mansion
possession by Oct 2027 · Dean Home LLP
Varsha
possession by Dec 2030 · Omshreemahavir Developers Private Limite
Varsha Galaxy
declared completion Jun 2025 · Omrameshwar CO-Operative Housing Society
Varshkrushna Heights
declared completion Jun 2024 · Krishna Thale & Kailash Thale
Varun
possession by Dec 2028 · Tryksha Real Estate Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026