Mumbai/Project record

MahaRERA · the public record

Vasant Harmony Business Park

Marol · HARMONY LIFESTYLE PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2029declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PC1180002501209

Delivery and registration

When is the project declared for completion?

Vasant Harmony Business Park is registered with MahaRERA as PC1180002501209 and the promoter has declared completion for 31 Dec 2029.

31 Dec 2029

declared completion

39months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPC1180002501209
Registered on13 Oct 2025
Promoter-declared completion31 Dec 2029
Current statusCertificate Signed
Against today39 months to the declared date

Promoter record

What else is this promoter on record for?

Harmony Lifestyle Projects is the promoter of record on 180 projects registered with MahaRERA, 43 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

180projects

registered with MahaRERA

43flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Vasant Harmony Business Park, ₹2.24 Cr of a declared ₹5.00 Cr estimated project cost is reported as incurred, about 44.8%, as at the last certified filing with MahaRERA.

44.8%

₹2.24 Cr

of ₹5.00 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vasant Harmony Business Park in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.

BuildingWingsFloorsDeclared completion
PROPOSED REDEVELOPMENT BUILDING1G+0-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Marol, Saki Vihar Road, Andheri, Mumbai Suburban, 400072. Per the filed land record, the plot is bounded to the north by CTS 678, to the south by Property Being Ruby Monarch Arcade & Beyond that by BMC Water Pipe Line, to the east by Saki Vihar Road and to the west by BMC Water Pipelines. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)6 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Powai

55 Corporate Avenue Building NO 2
possession by Dec 2026 · THE Cannonade Construction Company PVT L
Ibis At L And T Realty Elixir Reserve
possession by Dec 2026 · Larsen & Toubro Ltd.
Leo Heights
Not filing quarterly progress reports · possession by Dec 2026 · Sir George P Joseph
Somani 72 East
possession by Dec 2026 · Nircon Developers PVT LTD
72 Marina - Phase I - Tierra And Torres
possession by Dec 2026 · D S Developers
Crescent Silverwoods
possession by Dec 2026 · Crescent Shelters

Major developers building in Powai

Other RERA-registered projects in Mumbai Suburban

Vasant Heritage
possession by Dec 2026 · Pratham Developers
Vasant Kunj CHS LTD
declared completion Oct 2021 · Calvin Shresth Properties LLP
Vasant Oasis Camelia Bldg 13
declared completion Dec 2023 · Neepa Real Estates Private Limited
Vasant Oasis Daisy Bldg 18
declared completion Jun 2023 · Neepa Real Estates Private Limited
Vasant Oasis Danica Bldg NO 15
declared completion Dec 2022 · Neepa Real Estates Private Limited
Vasant Oasis Lillium Bldg 16
declared completion Dec 2023 · Neepa Real Estates Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026