Mumbai/Project record

MahaRERA · the public record

VASTU SHILP

birwadi · LAXMI CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000016075

Delivery and registration

When is the project declared for completion?

VASTU SHILP is registered with MahaRERA as P52000016075 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000016075
Registered on16 Apr 2018
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VASTU SHILP record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VASTU SHILP in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
VASTU SHILP1G+531 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at birwadi, main road, Mahad, Raigarh, 402302. Per the filed land record, the plot is bounded to the north by S NO2A AND 2B, to the south by INTERNAL ROAD, to the east by P NO 3 and to the west by OPEN SPACE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~123 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort117 km
Lower Parel / Worli business district123 km
Bandra Kurla Complex (BKC)127 km
Chhatrapati Shivaji Int'l Airport129 km
Powai / Hiranandani business park130 km
Andheri MIDC / SEEPZ133 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Laxmi Construction is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Laxmi Construction project & its RERA track record →

Other flagged projects by Laxmi Construction

Other RERA-registered projects in Birwadi

Hari OM Residency
possession by Dec 2026 · Aparna A Bhosale
Shelter Plaza
possession by Dec 2026 · Mahira Developers
SAI Prasad
possession by Dec 2027 · Dilip Waman Gadgil
Shiv Shalini Complex
possession by Dec 2028 · Ganarai Developers
Ekdant Enclave
possession by Dec 2032 · Not Available
Shreeji Corner
declared completion Jun 2024 · Shreeji Enterprise

Other RERA-registered projects in Raigarh

Vastu Vasant
declared completion May 2026 · Vastushilp Construction
Vastushilp
declared completion Aug 2023 · Ravindra Gopal Sant
Vatsala Keshav Plaza
declared completion Dec 2025 · Paras Builders AND Developers
Vatsala Maulikrupa
possession by Dec 2027 · Vatsala Land Developers Private Limited
Vatsalya Apartment
possession by Dec 2027 · M/s. Rehan Developers
Vatsalya Residency
possession by Jun 2028 · Vatsalya Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026