VINAYAK SHRADDHA TOWER

BANDRA EAST · K K KRISHNAN CONSTRUCTION COMPANY PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800003341

Delivery and registration

When is the project declared for completion?

VINAYAK SHRADDHA TOWER is registered with MahaRERA as P51800003341 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800003341
Registered on05 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VINAYAK SHRADDHA TOWER record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Krishnan Construction Company is the promoter of record on 9 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VINAYAK SHRADDHA TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
INDIRAKRUPA1G+14-
VINAYAK SHRADDHA TOWER1G+16-
MUNICIPAL PRIMARY SCHOOL1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2024It is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we
31 Dec 202431 Dec 2025We faced financial crisis during covid and were unable to raise funds, hence we introduced a co-promoter who agreed to fund the project construction. Our existing tenants of rehab

Location, Land & Connectivity

Located at BANDRA EAST , VIJAYNAGAR, Andheri, Mumbai Suburban, 400051. Per the filed land record, the plot is bounded to the north by SRA BUILDING, to the south by INTERNAL ROAD, to the east by SLUM and to the west by SRA UNDER CONSTRUCTION BLDG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Lower Parel / Worli business district7 km
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park8 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K K Krishnan Construction Company PVT LTD is the promoter on 4 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by K K Krishnan Construction Company PVT LTD

K K Krishnan Construction Company PVT LTD
Past its declared completion dateMumbai Suburban
K K Krishnan Construction Company PVT LTD
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Bandra East

A And O Estado
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Builders AND Developers
Antariksh Ace
possession by Dec 2026 · Pittie Antariksh Realty Private Limited
Bandra North Gulmohar Avenue
possession by Dec 2026 · Shivalik Ventures Private Limited
Gurukrupa Nirmalam
possession by Dec 2026 · Gurukrupa Realcon Infrastructure LLP
LEO Eminence
possession by Dec 2026 · LEO Infrastructure Private Limited
Mayur Tower
possession by Dec 2026 · Geopreneur Spire Realty

Major developers building in Bandra East

Other RERA-registered projects in Mumbai Suburban

Vindhyagiri
declared completion Dec 2025 · Gio Properties
Vintage
declared completion Dec 2023 · Vora Estates
Vir Enclave
declared completion Jun 2025 · JKD Engineers AND Infrastructure Private
VIR Paradise
possession by Nov 2027 · JKD Engineers AND Infrastructure Private
Vira Avenue
possession by Dec 2026 · Vira Realty India Private Limited
Vira ONE
possession by Dec 2026 · Grow More Builders AND Developers Privat

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026