Mumbai/Project record

MahaRERA · the public record

Vishnu Krupa

Badlapur · Patil Reality Group

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

20units filed as unsoldInventory · 20 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
20registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1330002500811

Delivery and registration

When is the project declared for completion?

Vishnu Krupa is registered with MahaRERA as PM1330002500811 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPM1330002500811
Registered on16 Sep 2025
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vishnu Krupa record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In Vishnu Krupa, 0 of 20 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 20 remain available.

0%sold

0 of 20 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 1Flat314 sqft (29.14 sqm)₹16.61 Lakh
Floor 2Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 2Flat314 sqft (29.14 sqm)₹16.61 Lakh
Floor 3Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 3Flat314 sqft (29.14 sqm)₹16.61 Lakh
Floor 4Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 4Flat314 sqft (29.14 sqm)₹16.61 Lakh
Floor 5Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 5Flat314 sqft (29.14 sqm)₹16.61 Lakh
Floor 6Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 6Flat314 sqft (29.14 sqm)₹16.61 Lakh
Floor 7Flat301 sqft (28 sqm)₹15.96 Lakh
Floor 7Flat314 sqft (29.14 sqm)₹16.61 Lakh
Upper GroundShop83 sqft (7.71 sqm)₹5.64 Lakh
Upper GroundShop97 sqft (9.03 sqm)₹6.60 Lakh
Upper GroundShop109 sqft (10.09 sqm)₹6.61 Lakh
Upper GroundShop101 sqft (9.39 sqm)₹6.15 Lakh
Upper GroundShop103 sqft (9.56 sqm)₹6.26 Lakh
Upper GroundShop52 sqft (4.87 sqm)₹3.56 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vishnu Krupa in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in Vishnu Krupa carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 20 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 5,295 a sq ft typical, over Rs 5,295 to Rs 6,791.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 20 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 20 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 20 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Vishnu Krupa1G+820-

Unit mix on the filing: 14 residential and 6 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Badlapur, Belavali, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by Road, to the south by Road, to the east by Road and to the west by Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park35 km
Andheri MIDC / SEEPZ39 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Vishnu Krupa Co Operative Housing Society
possession by Dec 2029 · Krishna Buildcon
Vishnu Shahu Construction
declared completion Apr 2024 · Vishnu Shahu Construction
Vishnu Shakuntal
declared completion Jul 2023 · Nayantara Cons
Vishnu Tower
declared completion Dec 2025 · Seema Vishnu Patil
Vishnu Vatika NX Phase II D & H Wing
possession by Oct 2026 · M/s. Vishnu Group
Vishnu Vatika Wing A AND B Phase I
declared completion May 2023 · Vishnu Vatika

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026