MahaRERA Property Intelligence · Thane

VISHNU TOWER

P51700018097 · ATALI · promoter Seema Vishnu Patil

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51700018097
Registered on10 Oct 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Seema Vishnu Patil is the promoter of record on 72 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~82.6% of the estimated project cost incurred as of the last certificate (₹3.79 Cr spent against a ₹4.59 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~82.6% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 36 homes filed with MahaRERA, 7 are sold/booked and 29 remain available (~19% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹1.97 Cr in agreement value so far. Of that, ₹1.34 Cr (~68%) is already collected, ₹62.56 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 7 registered agreements, the effective carpet rate is ₹5,148/sqft (typical range ₹4,686–₹8,395) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 11011,087 sqft (100.98 sqm)₹50.00 Lakh
Floor 1104390 sqft (36.2 sqm)₹2.00 Lakh
Floor 11051,189 sqft (110.46 sqm)₹50.00 Lakh
Floor 2202323 sqft (30 sqm)₹9.68 Lakh
Floor 2203454 sqft (42.19 sqm)₹23.00 Lakh
Floor 2204324 sqft (30.11 sqm)₹20.00 Lakh
Floor 3301323 sqft (30 sqm)₹9.68 Lakh
Floor 3302323 sqft (30 sqm)₹9.68 Lakh
Floor 3303323 sqft (30 sqm)₹9.68 Lakh
Floor 3304390 sqft (36.2 sqm)₹2.00 Lakh
Floor 3305323 sqft (30 sqm)₹9.68 Lakh
Floor 4401523 sqft (48.62 sqm)₹32.00 Lakh
Floor 4402323 sqft (30 sqm)₹9.68 Lakh
Floor 4403390 sqft (36.2 sqm)₹2.00 Lakh
Floor 4404324 sqft (30.11 sqm)₹20.00 Lakh
Floor 4405539 sqft (50.09 sqm)₹33.00 Lakh
Floor 5502454 sqft (42.19 sqm)₹23.00 Lakh
Floor 5505323 sqft (30 sqm)₹9.68 Lakh
Floor 6601323 sqft (30 sqm)₹9.68 Lakh
Floor 6602323 sqft (30 sqm)₹9.68 Lakh
Floor 6603323 sqft (30 sqm)₹9.68 Lakh
Floor 6604390 sqft (36.2 sqm)₹2.00 Lakh
Floor 6605323 sqft (30 sqm)₹9.68 Lakh
Floor 7701323 sqft (30 sqm)₹9.68 Lakh
Floor 7702323 sqft (30 sqm)₹9.68 Lakh
Floor 7703323 sqft (30 sqm)₹9.68 Lakh
Floor 7704390 sqft (36.2 sqm)₹2.00 Lakh
Floor 7705539 sqft (50.09 sqm)₹33.00 Lakh
Ground/Floor 0SHOP 1172 sqft (15.99 sqm)₹20.00 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0 and 36 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
VISHNU TOWER1G+03620 Dec 2020

Unit mix on the filing: 35 residential and 1 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
20 Dec 202131 Dec 2025Resp. Sir, I am requesting you to grant extension 31st December 2025, as we are currently in scarce of funds after Covid 19 impact and customers are also not willing to buy flats n
20 Dec 202130 Nov 2022With respect to above subject, I, Seema Vishnu Patil (Proprietor of Vishnu Developers) promoter of Project Vishnu Tower bearing Reg. No. P51700018097 under MahaRera Act., request y

Location, Land & Connectivity

Located at ATALI, ATALI VILLAGE ROAD, Kalyan, Thane, 421102. Per the filed land record, the plot is bounded to the north by 755, to the south by ROAD 15, to the east by 756 and to the west by 745. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambivali West

Godrej Riviera Phase 1
possession by Dec 2026 · Godrej Properties Limited
Pearl Galaxy
possession by Dec 2026 · Pearlcorporates
Gaikwad Residency
possession by Dec 2026 · Niwara Group
Gangubai Height
possession by Dec 2026 · Vinayak Construction
Ashapura Galaxy
possession by Mar 2027 · Ashapura Estates
Lotus Residency
possession by Mar 2027 · Kulvinder Infrastructure Private Limited

Other RERA-registered projects in Thane

Vishnu Vatika NX Phase II D & H Wing
possession by Oct 2026 · M/s. Vishnu Group
Vishnu Vatika NX Wing C1 E1 E2 Phase 1
declared completion Oct 2023 · Vishnu Group
Vishnu Vatika Wing A AND B Phase I
declared completion May 2023 · Vishnu Vatika
Vishnu Vatika Wing C Phase II
possession by Dec 2026 · Vishnu Vatika
Vishnu Vertex
possession by Mar 2031 · Vishnu Bihar Builders AND Developers LLP
Vishv Eleanor
possession by Aug 2026 · Vishv Realty

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.