MahaRERA Property Intelligence · Mumbai Suburban

Wishvas

P51800022789 · Bhandup West · promoter Aakaar Nirmaan Properties

Certificate SignedDue 30 Dec 2025

Delivery & Registration

MahaRERA registrationP51800022789
Registered on25 Oct 2019
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aakaar Nirmaan Properties is the promoter of record on 32 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+30.

BuildingWingsFloorsDeclared completion
SALE 11G+831 Dec 2024
SALE 21G+3031 Dec 2024

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000030303913/10/2022SANKET SHANTARAM AMBADASKAR vs TUSHAR BABULAL KUVADIAorder passed
CC00600000043971422/03/2024Babu Sahadev Chavan vs HARSH PARESH SHAHorder passed
CC1250275906/08/2025MAHESH Tulsidas Mayekar vs AAKAAR NIRMAAN PROPERTIESorder passed

Legal & Litigation

The promoter has declared 9 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Citiy Civil Court Mumbai10292017For Service Or Hearing Of Chamber Summons
City Civil Court Mumbai9892017For Service Or Hearing Of Chamber Summons
City Civil Court Mumbai16572017For Service Or Hearing Of Chamber Summons
City Civil Court Mumbai15892017Nm For Hearing
City Civil Court Mumbai14302017For Service Or Hearing Of Chamber Summons
City Civil Court Mumbai14042017For Further Evidence Of The Plaintiff
High Court Of Mumbai10932018Pre Admission For Direction
City Civil Court Mumbai13332017For Service Or Hearing Of Chamber Summons
High Court Of Mumbai7232016Pre Admission For Direction

Location, Land & Connectivity

Located at Bhandup West, Sahyadri Nagar, Kurla, Mumbai Suburban, 400078. Per the filed land record, the plot is bounded to the north by Samarth Nagar Road, to the south by Proposed 6mtrLayout Road, to the east by Existing Sardar Pratap Singh Road and to the west by CTS 247. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Wisteria Residency
declared completion Dec 2023 · Vaibhav Realtors
Woodland Mulund CHS LTD
declared completion Dec 2025 · Sunrise Housing
Woodlands Reserve
possession by Mar 2030 · Upvan Developers
Woods Platina Wing B- Ebony Tower
declared completion Jul 2024 · Sukoon Developers Pvt Ltd
Woods Platina Wing C - Walnut Tower
possession by Dec 2026 · Sukoon Developers Pvt Ltd
Woods Platina Wing D - Oak Tower
possession by Dec 2026 · Sukoon Developers Pvt Ltd

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026