Xrbia Warai / Neral - Ph 1

Warai · XRBIA WARAI DEVELOPERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000002828

Delivery and registration

When is the project declared for completion?

Xrbia Warai / Neral - Ph 1 is registered with MahaRERA as P52000002828 and the promoter has declared completion for 29 Dec 2022.

29 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000002828
Registered on04 Aug 2017
Promoter-declared completion29 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Xrbia Warai / Neral - Ph 1 record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Xrbia Warai Developers is the promoter of record on 28 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

28projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Xrbia Warai / Neral - Ph 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A11G+431 Dec 2020
A21G+431 Dec 2020
A51G+831 Dec 2020
A61G+831 Dec 2020
A71G+831 Dec 2020
A81G+831 Dec 2020
B11G+431 Dec 2020
B21G+431 Dec 2020
B31G+431 Dec 2020
C51G+431 Dec 2020
D11G+431 Dec 2020
D21G+431 Dec 2020
D31G+431 Dec 2020
D41G+431 Dec 2020
D51G+431 Dec 2020
D61G+431 Dec 2020
E21G+431 Dec 2020

Legal and disputes

What disputes are disclosed?

28 complaints are on the MahaRERA record for Xrbia Warai / Neral - Ph 1, with orders passed in 28 of them.

28complaints

28with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020958131/12/2021DEVESH AJIT JOSHI & VANITA AJIT JOSHI vs XRBIA WARAI DEVELOPERS PVT. LTDorder passed
CC00600000005671824/10/2018SUCHITA ULHAS TAWADE vs XRBIA DEVELOPERS LTDorder passed
CC00600000005675229/10/2018MOHAMMED ISHAQUE SURVE vs M/S XRBIA DEVELOPERS LTD.order passed
CC00600000005689231/12/2018SHABANA GULAMKADAR SHAIKH vs XRBIA DEVELOPERS LTDorder passed
CC00600000005764912/09/2019TANUJA SAMEER RAJE vs XRBIA DEVELOPERS LTDorder passed
CC00600000005744327/12/2018Pritam Runwal vs Xrbia Warai Developers Pvt. Ltd.order passed
CC00600000005806914/02/2019FAIYAZ HAMID BAGBAN vs Xrbia Warai Development Pvt Ltdorder passed
CC00600000007888414/04/2019deepti Prashant Sonawane vs Xrbia Developers Limitedorder passed
CC00600000007948827/05/2019Pooja Ajay Pradhan vs Xrbia Warai Developers Pvt. Ltd.order passed
CC00600000012099326/01/2020Vinaya Shingre vs Xrbia Warai Dev PVT LTDorder passed
CC00600000018197003/01/2020Vinay Prabhakar Pawar vs Karan Rajivkumar Karnawatorder passed
CC00600000019215822/01/2020MR. PARKAR BASHIR AHMED DAWOOD vs xrbia developers ltdorder passed
CC00600000019281809/03/2020Arvind Rajadhyaksha vs Xrbia Warai Developers Pvt Ltdorder passed
CC00600000019340909/07/2020Manisha ajit Kamble vs xrbia developers limitedorder passed
CC00600000019597610/02/2021Sayed Mairaj Asad Raza vs Xrbia Developers Ltdorder passed
CC00600000019726728/06/2021Asmita Vijay Pal vs XRBIA WARAI DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019733928/06/2021AJAY RAMJEET PAL vs XRBIA WARAI DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000020987031/01/2022RESHMABEE MOHAMMED SAIFUDDIN SHAIKH NEE RESHMABEE SUHAIL PATANKAR RESHMABEE MOHAMMED SAFIUDDIN SHAIK vs XRBIA WARAI DEVELOPERS PVT LTDorder passed
CC00600000019873219/10/2021SHRIDHAR APPA BARKOL vs XRBIA WARAI DEVELOPERS PVT LTDorder passed
CC00600000019906906/12/2021Herain Gangadharan Belcheda vs Xrbia Warai Developers Pvt Ltdorder passed
CC00600000019912523/11/2021VANDANA PAI vs M/S. Xrbia Wari Developers Pvt Ltdorder passed
CC00600000020954425/12/2021Vandana Pai vs XRBIA WARAI DEVELOPERS PVT LTDorder passed
CC00600000020957231/12/2021Vinodraj Bhaskarrao Thodeti vs Xrbia Warai Developers Private Limitedorder passed
CC00600000039669419/07/2023Ajay Keshav Patole vs XRBIA WARAI Developers Pvt. Ltd.order passed
CC00600000039679126/07/2023MAYA PRABHU vs Xrbia Warai Development Private Limitedorder passed
CC00600000039711717/08/2023PARMINDER KALIA vs XRBIA WARIA DEVELOPERS PVT LTDorder passed
CC00600000040845421/12/2023Sophina Rickson Dias vs M/s. Xrbia Warai Developers Pvt. Ltd.order passed
CC1250117308/04/2025Mrs. Linda Ann Eustace Dsouza vs XRBIA WARAI DEVELOPERS PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2022Construction activity couldn’t be carried out during year 2019 due to excessive rainfall in the project area. Also Reduced Labour and Material availability due to continued and int

Location, Land & Connectivity

Located at Warai, Warai, Pune City, Pune, 410201. Per the filed land record, the plot is bounded to the north by RIVER, to the south by SR NO 6 8 9 13, to the east by SR NO 13 VILLAGE BO and to the west by S NO 10. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~53 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park53 km
Bandra Kurla Complex (BKC)56 km
Chhatrapati Shivaji Int'l Airport56 km
Andheri MIDC / SEEPZ57 km
Lower Parel / Worli business district59 km
Nariman Point / Fort61 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Xrbia Warai Developers Private Limited is the promoter on 7 MahaRERA-registered projects, of which 7 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Xrbia Warai Developers Private Limited project & its RERA track record →

Other flagged projects by Xrbia Warai Developers Private Limited

Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Raigarh
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Raigarh

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Xrbia Warai / Neral - Ph 2
declared completion Dec 2022 · Xrbia Warai Developers Private Limited
Xrbia Warai / Neral - Ph 3
declared completion Mar 2023 · Xrbia Warai Developers Private Limited
Yadav Residency
declared completion Dec 2022 · Rajendra Yadav Bhagat
Yakub Kachchi Heights
declared completion Dec 2024 · Build Well Enterprises
Yamuna
possession by Dec 2026 · Channel Homes LLP
Yamuna Niwas
possession by Jul 2027 · M/s Vighnaharta Properties

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026