MahaRERA Property Intelligence · Raigarh

Xrbia Warai / Neral - Ph 3

P52000002246 · Warai · promoter Xrbia Warai Developers

Certificate SignedDue 30 Mar 2023

Delivery & Registration

MahaRERA registrationP52000002246
Registered on31 Jul 2017
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Xrbia Warai Developers is the promoter of record on 27 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
A91G+831 Mar 2022
A101G+831 Mar 2022
B51G+831 Mar 2022
C101G+631 Mar 2022
K51G+631 Mar 2022
K91G+831 Mar 2022

Complaints & Orders

3 complaints are on the MahaRERA record for this project, with orders passed in 3. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019659614/08/2021Malhari Baban Gayke vs XRBIA WARAI DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019891814/11/2021VINAY HARISHCHANDRA KOREGAONKAR vs XRBIA DEVELOPER (GAJANAN DHOGRE)order passed
CC00600000019893109/11/2021AasmaThakur vs Xrbia warai developers pvt ltd.order passed

Location, Land & Connectivity

Located at Warai, Warai, Pune City, Pune, 410201. Per the filed land record, the plot is bounded to the north by RIVER, to the south by S NO 6 8 9 13, to the east by SR NO 13 VILLAGE BO and to the west by S NO 10. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~53 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park53 km
Bandra Kurla Complex (BKC)55 km
Chhatrapati Shivaji Int'l Airport56 km
Andheri MIDC / SEEPZ57 km
Lower Parel / Worli business district59 km
Nariman Point / Fort61 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Xrbia Warai Developers Private Limited is the promoter on 7 MahaRERA-registered projects, of which 7 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Xrbia Warai Developers Private Limited project & its RERA track record →

Other flagged projects by Xrbia Warai Developers Private Limited

Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Thane
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Raigarh
Xrbia Warai Developers Private Limited
Developer in insolvency (NCLT)Raigarh

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Yakub Kachchi Heights
declared completion Dec 2024 · Build Well Enterprises
Yamuna
possession by Dec 2026 · Channel Homes LLP
Yamuna Hari Niwas
declared completion Mar 2023 · Smita Enterprises
Yamuna Niwas
possession by Jul 2027 · M/s Vighnaharta Properties
Yamuna Residency
declared completion Mar 2024 · Prasad Anant Desai
YAS
declared completion Dec 2021 · Prodigar Developers Private Limited

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026