Mumbai/Project record

MahaRERA · the public record

YARK HILLS

SHELWALI · R R BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

49units filed as unsoldInventory · 16 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
70registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000054009

Delivery and registration

When is the project declared for completion?

YARK HILLS is registered with MahaRERA as P99000054009 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000054009
Registered on19 Dec 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for YARK HILLS record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In YARK HILLS, 0 of 49 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 49 remain available.

0%sold

0 of 49 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 70 homes in total, while this sold/unsold inventory filing covers 49 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 21 owner/investor-held.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for YARK HILLS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 16 September 2026

What the filings record, home by home

Read from MahaRERA on 16 September 2026

No home in YARK HILLS carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 70 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 2,999 a sq ft typical, over Rs 2,851 to Rs 4,996.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 70 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 70 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 70 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 2, WING A , TYPE B21G+77031 Dec 2027

Unit mix on the filing: 57 residential and 13 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SHELWALI, SHELWALI, Vasai, Palghar, 401401. Per the filed land record, the plot is bounded to the north by BUILDING, to the south by OPEN LAND, to the east by BUILDING and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~62 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park62 km
Andheri MIDC / SEEPZ64 km
Chhatrapati Shivaji Int'l Airport67 km
Bandra Kurla Complex (BKC)68 km
Lower Parel / Worli business district76 km
Nariman Point / Fort82 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

R R Builders & Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every R R Builders & Developers project & its RERA track record →

Other RERA-registered projects in Kelve Road

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
possession by Dec 2026 · Sai Builders And Developers
Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · possession by Dec 2026 · Savera Builders & Developers
THE Hill Touch
possession by Dec 2026 · Aristone Infra
SK Swarnik Homes
possession by Feb 2027 · SK Swarnik Homes

Other RERA-registered projects in Palghar

Yash Apartment
declared completion Dec 2025 · Kush Ramsingar Vishwakarma
Yash Apartment
declared completion Mar 2025 · Ramsingar Yadav
Yash Padma
possession by Dec 2026 · SAI Shraddha Enterprises
Yash Padma Phase II
possession by Dec 2030 · SAI Shraddha Enterprises
Yash Reality
declared completion Jun 2023 · Yash Reality
Yashoda Apartment
possession by Dec 2026 · Panchavati Builders AND Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.