Yashwant Datt Greens II

Opp. Spring Avenue · OMKAR REALTY

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10 Sep 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

10 Sep 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000030400

Delivery and registration

When is the project declared for completion?

Yashwant Datt Greens II is registered with MahaRERA as P99000030400 and the promoter has declared completion for 10 Sep 2025.

10 Sep 2025

declared completion

12months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000030400
Registered on20 Aug 2021
Promoter-declared completion10 Sep 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Yashwant Datt Greens II record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Omkar Realty is the promoter of record on 162 projects registered with MahaRERA, 23 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

162projects

registered with MahaRERA

23flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Yashwant Datt Greens II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Row House - 11G+110 Sep 2025
Row House - 21G+110 Sep 2025
Row House - 31G+110 Sep 2025
Row House - 41G+110 Sep 2025
Row House - 61G+110 Sep 2025
Row House - 71G+110 Sep 2025
Row House - 81G+110 Sep 2025
Row House - 91G+110 Sep 2025
Row House - 51G+110 Sep 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Opp. Spring Avenue, Manvel Pada Road, Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by Open plot, to the south by Road, to the east by Yashwant Datt Green Bungalow and to the west by Yashvidya Niketan School. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Omkar Realty is the promoter on 4 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Omkar Realty

Omkar Realty
Past its declared completion datePalghar

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Radheya Enterprises
possession by Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
possession by Dec 2026 · VED Ganga

Other RERA-registered projects in Palghar

Yashwant Prestige
possession by Apr 2027 · RAJ Enterprises
Yashwant Sankalp- Jasmin Phase 2
declared completion Jul 2025 · Mahalaxmi Infra
Yesha Arcadia
possession by Dec 2026 · Yashobhumi Construction
Yeshwant Vinayak Complex
declared completion May 2025 · Shree Chintamani Developers
Yog Vihar
possession by Mar 2029 · Dhaval Pravin Vira
Yogini Residency
declared completion Dec 2017 · Pankaj Balkrishna Jadhav

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.