Aapla Ghar Paud 2 Phase I

Pune · Phoenix Ventures

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100002798

Delivery and registration

When is the project declared for completion?

Aapla Ghar Paud 2 Phase I is registered with MahaRERA as P52100002798 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100002798
Registered on04 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aapla Ghar Paud 2 Phase I record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Phoenix Ventures is the promoter of record on 27 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

27projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aapla Ghar Paud 2 Phase I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
C1G+931 Dec 2022
D1G+931 Dec 2022
F1G+931 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Aapla Ghar Paud 2 Phase I, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000000004407/08/2017Sharad Ashok Agarwal vs Sachin Ashok Agarwalorder passed

Location, Land & Connectivity

Located at Pune City, Pune, 412208. Per the filed land record, the plot is bounded to the north by Adjacent Gat No 88, to the south by Future Development and remaining part of same gat, to the east by Shiv Road and to the west by Remaining part of same gat. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park14 km
Baner–Balewadi belt16 km
Pune Junction / city centre26 km
Magarpatta / Hadapsar IT31 km
Pune Int'l Airport (Lohegaon)31 km
Kharadi / EON IT Park33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Phoenix Ventures is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Phoenix Ventures project & its RERA track record →

Other RERA-registered projects in Shikrapur

Sharanya Galaxy
possession by Dec 2026 · Sharanya Constructions
Harmony
possession by Dec 2026 · Nandakumar Lapalikar
Abhilasha Wing A AND Wing B
possession by Dec 2026 · M/S Kudale Sable Builders
Maitri Gold
possession by Dec 2026 · Maitri Developers AND Builders
Patil Plaza
Not filing quarterly progress reports · possession by Dec 2026 · Devidas Patil
Rustic Meadows
possession by Dec 2026 · Sanjay Gopichand Jasuja

Major developers building in Shikrapur

Other RERA-registered projects in Pune

Aapla Ghar Ranjangaon Phase II
possession by Dec 2026 · Maple City Developers
Aapla Ghar Urali Kanchan Lakeside Phase 1
declared completion Dec 2022 · Maple Shelters Uralikanchan 1
Aapla Ghar Wagholi Annex 2 Phase I
declared completion Dec 2023 · Maple Homes LLP
Aapla Ghar Wagholi Annex Phase I
possession by Dec 2026 · Maple Indus Developers
Aaradhya
declared completion Jan 2025 · Gruhpurti Realtors LLP
Aaradhya City Centre
declared completion Mar 2025 · Digambar Dnyandeo Patil

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026