Pune/Project record

MahaRERA · the public record

Aapla Ghar Urali Kanchan Lakeside Phase 1

Pune · Maple Shelters Uralikanchan 1

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100003456

Delivery and registration

When is the project declared for completion?

Aapla Ghar Urali Kanchan Lakeside Phase 1 is registered with MahaRERA as P52100003456 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100003456
Registered on05 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Aapla Ghar Urali Kanchan Lakeside Phase 1 record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Aapla Ghar Urali Kanchan Lakeside Phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
A51G+931 Dec 2021
A61G+531 Dec 2021
Proposed1-31 Dec 2021

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for Aapla Ghar Urali Kanchan Lakeside Phase 1, with orders passed in 10 of them.

10complaints

10with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000023862231/03/2023NAVNATH SHIVAJI LONDHE vs maple sheltresorder passed
CC00500000002263411/02/2019Marathe Asha Pandurang vs M/s. Maple Shelters Uralikanchan 1order passed
CC00500000004370709/12/2019Aman Shamsuddin Shah vs Sachin Ashok Agarwalorder passed
CC00500000004371509/12/2019Wasim Munwar Shaha vs M/s Maple Shelters Uralikanchan 1order passed
CC00500000005415716/03/2020MAHENDRA RAJENDRA GIRME vs SACHIN ASHOK AGARWALorder passed
CC00500000006430022/06/2020v r kothavale vs Sachin Ashok Agarwalorder passed
CC00500000006444430/08/2020VaishaliBagdeGanesh vs M/s Maple Shelters Uralikanchan 1order passed
CC00500000007509818/01/2021Bharat Sohan Raj Rathod vs Mapel Shelters Uruli Kanchan 1order passed
CC00500000010650405/02/2022Vijay Namdeo Mane vs Ellora Developers, Through its partner 1) Bharat Rathod, 2) Meena Rathodorder passed
CC1250017319/01/2025vidyashree ramesh kothavale vs Maple Shelters Uralikanchan 1order passed

Location, Land & Connectivity

Located at Pune City, Pune, 412202. Per the filed land record, the plot is bounded to the north by Future Development on remaining plot, to the south by Adjacent gat no 756, to the east by Adjacent Gat No 773 and to the west by Adjacent Gat No 774. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Pune Junction / city centre9 km
Hinjewadi Rajiv Gandhi IT Park11 km
Magarpatta / Hadapsar IT14 km
Pune Int'l Airport (Lohegaon)16 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Uruli Kanchan

Siddhi Sankul
possession by Sep 2026 · Jitendra Constructions AOP
Elite II
Not filing quarterly progress reports · possession by Dec 2026 · Landmark Development Corporation PVT LTD
Srinivas Empire
Not filing quarterly progress reports · possession by Mar 2027 · Srinivas And Associates
Sahyadri
possession by Aug 2027 · Sahyadri Builders And Developers
Green Fantasy Phase-I
possession by Dec 2027 · Shree Mangalmurti Associates Phase-I
Sunrise Villa
possession by Dec 2027 · White House Construction

Other RERA-registered projects in Pune

Aapla Ghar Wagholi Annex 2 Phase I
declared completion Dec 2023 · Maple Homes LLP
Aapla Ghar Wagholi Annex Phase I
possession by Dec 2026 · Maple Indus Developers
Aaradhya
declared completion Jan 2025 · Gruhpurti Realtors LLP
Aaradhya City Centre
declared completion Mar 2025 · Digambar Dnyandeo Patil
Aaradhya Heights
declared completion Oct 2025 · Aaradhya Developers
Aaradhya Heights
possession by Mar 2028 · Balaji Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026