Pune/Project record

MahaRERA · the public record

AMRUT PUSHP

DUDULGAON · MORAYA REALITY GROUP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100011364

Delivery and registration

When is the project declared for completion?

AMRUT PUSHP is registered with MahaRERA as P52100011364 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100011364
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AMRUT PUSHP record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AMRUT PUSHP in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
A WING1G+631 Dec 2019
B WING1G+131 Dec 2019

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for AMRUT PUSHP, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000017795017/12/2022Digambar Shrikant Patil vs RAMKRUSHNA PUNDEorder passed
CC00500000019800028/12/2022Savita Anant Ghagare vs RAMKRISHNA BABAN PUNDEorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 202090% of our project is completed, hence we request for extension of the project.

Location, Land & Connectivity

Located at DUDULGAON, DUDULGAON, Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by PROPERTY BELONGS TO MR VAHILE, to the south by ROAD, to the east by GAT NO 244 AND PROPERTY BELONGS TO MR GAIKWAD and to the west by PROPERTY BELONGS TO MR JIJABA FALKE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~105 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park105 km
Baner–Balewadi belt110 km
Pune Junction / city centre121 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park126 km
Magarpatta / Hadapsar IT126 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Amruta Vihar
possession by Dec 2027 · Amruta Developers
Amrutkalash
possession by Dec 2027 · Amrutkalash Properties
Amrutvel
possession by Mar 2027 · Shivmudra Enterprises
Amrutwel Residency
declared completion Jun 2022 · Swarajaya Promoters & Builders
Amrutyog Residency
possession by Dec 2029 · Deepchandra Developers Private Limited
Anadgram Bhandgaon Building G
declared completion Jul 2023 · Vastushodh Infrastructure LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026