ATULYA RAGHUKUL BUILDING NO.D

WADMUKHWADI · Calyx Lenora Realty LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100017929

Delivery and registration

When is the project declared for completion?

ATULYA RAGHUKUL BUILDING NO.D is registered with MahaRERA as P52100017929 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100017929
Registered on27 Sep 2018
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ATULYA RAGHUKUL BUILDING NO.D record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Calyx Lenora Realty is the promoter of record on 7 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ATULYA RAGHUKUL BUILDING NO.D in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
D1G+1930 Jun 2023

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for ATULYA RAGHUKUL BUILDING NO.D, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000047146506/08/2024Atulya Raghukul Apartment Association vs Calyx Lenora Realty LLPorder passed
CC1250236011/07/2025KIRAN DAGDU JADHAV vs Calyx Lenora Realty LLPorder passed

Location, Land & Connectivity

Located at WADMUKHWADI, SPINE ROAD, Pune City, Pune, 412105. Per the filed land record, the plot is bounded to the north by 18 MW DP ROAD, to the south by OPEN SPACE, to the east by ATULYA MUKTAINAGAR - E BLDG and to the west by ATULYA MUKTAINAGAR - C BLDG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)8 km
Kharadi / EON IT Park12 km
Pune Junction / city centre13 km
Baner–Balewadi belt15 km
Magarpatta / Hadapsar IT15 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Calyx Lenora Realty LLP is the promoter on 7 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Calyx Lenora Realty LLP

Calyx Lenora Realty LLP
Past its declared completion datePune
Calyx Lenora Realty LLP
Past its declared completion datePune
Calyx Lenora Realty LLP
Past its declared completion datePune
Calyx Lenora Realty LLP
Past its declared completion datePune
Calyx Lenora Realty LLP
Not filing quarterly progress reportsPune
Calyx Lenora Realty LLP
FlaggedPune

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Atulyam-Inclusive Housing
possession by Dec 2027 · Shubh Housing
Atur Valley Vista Wing A
possession by Dec 2027 · M/S Atur Sangtani AND Associates
Audumbar
possession by Dec 2028 · Belvalkar Housing LLP
Audumbar
possession by Dec 2028 · Not Available
Audumbar Bliss
possession by Dec 2026 · Royal Srushti Developers
Audumbar Bliss
possession by Dec 2029 · ABS Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.