01 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100026156

Delivery and registration

When is the project declared for completion?

BALAJI SUDARSHAN is registered with MahaRERA as P52100026156 and the promoter has declared completion for 01 Jun 2025.

01 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100026156
Registered on25 Aug 2020
Promoter-declared completion01 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BALAJI SUDARSHAN record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shri Balaji Sudarshan is the promoter of record on 30 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

30projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BALAJI SUDARSHAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHRINIVASA GOVINDA NIVAS1G+601 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at 507 GURUWAR PETH, MAHARANA PRATAP , Pune City, Pune, 411042. Per the filed land record, the plot is bounded to the north by CTS NO 515 GURUWAR PETH PUNE 411042, to the south by ROAD, to the east by CTS NO 506 GURUWAR PETH PUNE411042 and to the west by CTS NO 508 GURUWAR PETH PUNE 411042. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shri Balaji Sudarshan is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shri Balaji Sudarshan

Shri Balaji Sudarshan
Deregistered by MahaRERAPune

Other RERA-registered projects in Guruwar Peth

Sanghvi Premio
possession by Oct 2026 · Nitin Kantilal Sanghvi
Samaira Tower
possession by Nov 2026 · Prathamesh Constro Realty Llp
Shri Balaji Sudarshan
Deregistered by MahaRERA · possession by Dec 2026 · Shri Balaji Sudarshan
Radiance
Not filing quarterly progress reports · possession by Dec 2026 · Mohammed Sabir Husain Shaikh
Siddhi Plaza
possession by Dec 2026 · Shree Developers
TEJ Nova
possession by Dec 2027 · Tejraj Profile Infra LLP

Other RERA-registered projects in Pune

Balaji Vishwa
declared completion Jun 2023 · Ideal Developers
Balaji Vishwa Building D AND E
declared completion Sep 2025 · Ideal Properties
Balaji Vishwa Phase - II
declared completion Sep 2025 · JAY Balaji Developers
Balboa Avenue Phase 1
declared completion Jan 2018 · Ravie Khilumal Ochanni
Balewadi 37
declared completion Apr 2024 · Nitin Shamrao Patil
Balkrishna Residency 2
declared completion Dec 2023 · Balkrishna Associates

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026