Pune/Project record

MahaRERA · the public record

BHAMINI ARCADE

Pune · Sanjay Dattatraya Dapodikar

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100010691

Delivery and registration

When is the project declared for completion?

BHAMINI ARCADE is registered with MahaRERA as P52100010691 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100010691
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BHAMINI ARCADE record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sanjay Dattatraya Dapodikar is the promoter of record on 38 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

38projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BHAMINI ARCADE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
BHAMINI ARCADE1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2020Now we need a further a period of about 9 months to complete the rest of the work mention above. In view of the above we humbly request that we may be permitted to extended the p

Location, Land & Connectivity

Located at Haveli, Pune, 411030. Per the filed land record, the plot is bounded to the north by S NO 119, to the south by PUNE SINHGAD ROAD, to the east by S NO 120 and to the west by S NO 125. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre6 km
Baner–Balewadi belt9 km
Magarpatta / Hadapsar IT10 km
Kharadi / EON IT Park13 km
Pune Int'l Airport (Lohegaon)13 km
Hinjewadi Rajiv Gandhi IT Park15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Sadashiv Peth

Krishna Kamal
possession by Sep 2026 · Vakratund Reality
Rukmini Niwas
possession by Sep 2026 · R. B. Chaphalkar Homes Pvt. Ltd.
SAI - Lalitha
possession by Dec 2026 · Sairam Developers
9 Sadashiv C Building
possession by Dec 2026 · Pinnacle Neostar Corporation Pvt. Ltd.
Sadashiv Vishnu
Not filing quarterly progress reports · possession by Dec 2026 · Sadashiv Vishnu Realty LLP
Enjays Paramount
possession by Dec 2026 · Enjay Infra

Major developers building in Sadashiv Peth

Other RERA-registered projects in Pune

Bharat Leelaa
possession by Dec 2030 · Bharat Leelaa Developers
Bharat Sohanraj Rathod
declared completion Dec 2019 · Bharatkumar Rathod
Bharatshree
declared completion Mar 2022 · Darode JOG Redevelopment PVT LTD
Bhardwaj
declared completion Mar 2026 · Motive Associates
Bhargav Amantra
declared completion Dec 2024 · Bhargav Homes
Bhargav Bellina
declared completion Jun 2025 · Bhargav Buildcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026