MahaRERA Property Intelligence · Pune
P52100002694 · ERANDWANE · promoter Darode Jog Redevelopment
| MahaRERA registration | P52100002694 |
| Registered on | 02 Aug 2017 |
| Promoter-declared completion | 30 Mar 2022 |
| Current status | Certificate Signed |
| Against today | about 52 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Darode Jog Redevelopment is the promoter of record on 18 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| A WING | 1 | G+7 | 30 Sep 2021 |
| B WING | 1 | G+7 | 30 Sep 2021 |
| C WING | 1 | G+7 | 30 Sep 2021 |
| D WING | 1 | G+7 | 30 Sep 2021 |
| E WING | 1 | G+7 | 30 Sep 2021 |
| Club House | 1 | G+2 | - |
6 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC005000000010395 | 11/10/2017 | Bharatshree Society vs Darode Jog Redevelopment P. Ltd | order passed |
| CC005000000106618 | 11/02/2022 | Bharatshree Housing Society (society) vs Darode Jog Redevelopment P Ltd | order passed |
| CC005000000033496 | 01/10/2019 | Bharatshree Housing Society (society) vs Darode Jog Redevelopment P. Ltd. | order passed |
| CC005000000064921 | 10/12/2020 | Sunil Mahindra Katkar vs Darode- Jog | order passed |
| CC005000000096050 | 23/09/2021 | MRS KAVERI ASHOK HARPALE MR ASHOK LAXMAN HARPALE vs Bharatshree cooperative housing society ltd | order passed |
| CC12502096 | 26/06/2025 | SIVADASAN R R vs DARODE JOG REDEVELOPMENT PVT LTD | pending / no order on file |
⚠ A co-operative housing society is the complainant here (Bharatshree Housing Society) and MahaRERA has already passed an order. On a redevelopment, that is the LANDOWNER society in dispute with its developer — a different order of risk from a single buyer's grievance, because it can touch the development rights, the society's consent, and ultimately the title to your flat. Have your lawyer read this order and the development agreement together before you commit.
The promoter has declared 6 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Jmfc Pune | 16053/2015 | 2015 | Filing Claim Affidavit By The Complainant |
| Cjsd | 1 | 2021 | Appealed |
| Cjsd | 2 | 2021 | Appealed |
| Adj | 89 | 2021 | Stay Vacated |
| Adj | 90 | 2021 | Stay Vacated |
| Bombay High Court | 10848 | 2021 | Appeal Dismissed |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Mar 2022 | 30 Sep 2021 | Reconciliation is in process with Mr Shirish Mulekar and Mr. Amar Manjrekar and next date is 20th Aug 2019. In the counselling date for possession is 30th June 2020. |
Located at ERANDWANE, BHARATKUNJ, Pune City, Pune, 411038. Per the filed land record, the plot is bounded to the north by SNo 103 CTS NO 141, to the south by By Road and S No 39, to the east by By S No 37 and to the west by By S No 104 part . Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~75 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 75 km |
| Baner–Balewadi belt | 81 km |
| Pune Junction / city centre | 91 km |
| Pune Int'l Airport (Lohegaon) | 92 km |
| Kharadi / EON IT Park | 96 km |
| Magarpatta / Hadapsar IT | 97 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in BHARATSHREE?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026