MahaRERA Property Intelligence · Pune

Bluegrass Business Park - Tower B

P52100025080 · Yeravada · promoter Farrokh Framji Wadia

Certificate SignedDue 30 Dec 2028

Delivery & Registration

MahaRERA registrationP52100025080
Registered on18 Mar 2020
Promoter-declared completion30 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Farrokh Framji Wadia is the promoter of record on 3 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Bluegrass Business Park Tower - II1G+1731 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Yeravada, Nagar Road, Pune City, Pune, 411006. Per the filed land record, the plot is bounded to the north by Nagar Road, to the south by Final Plot 3 By 3 Part, to the east by Final Plot 3 by 1 and Final Plot 3 by 2 and to the west by Nagar Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre3 km
Pune Int'l Airport (Lohegaon)5 km
Kharadi / EON IT Park5 km
Magarpatta / Hadapsar IT5 km
Baner–Balewadi belt12 km
Hinjewadi Rajiv Gandhi IT Park17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Farrokh Framji Wadia is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Farrokh Framji Wadia project & its RERA track record →

Other flagged projects by Farrokh Framji Wadia

Other RERA-registered projects in Yerwada

Bluegrass Residences Tower III
possession by Dec 2026 · Sagitarius Ecospaces LLP
Belmont Lunar
possession by Mar 2027 · Prasad Balasaheb Shinde
Vaishnavi Ouranos
possession by Dec 2027 · Vaishnavi & OM Construction
Power Terrace
possession by Mar 2028 · Sapra Builders
River Vista
possession by Mar 2028 · Rahul Shubham LLP
Sheetal Park CO-Operative Housing Society LTD
possession by Mar 2028 · Belvalkar Housing LLP

Major developers building in Yerwada

Other RERA-registered projects in Pune

Bluegrass Residences - Tower I
declared completion Apr 2025 · Sagitarius Ecospaces LLP
Bluegrass Residences Tower II
declared completion Apr 2026 · Sagitarius Ecospaces LLP
Bluegrass Residences Tower III
possession by Dec 2026 · Sagitarius Ecospaces LLP
Blueridge-The Groves
declared completion Jun 2026 · Nova Developers PVT LTD
Blueroof Sylva
possession by Jun 2030 · SS Properties
Bollywood Hills
declared completion Dec 2022 · Vishwaraj Construction

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026