Pune/Project record

MahaRERA · the public record

CHINAR CONDOMINIUM

shivajinagar · ganesh dnyaneshwar chavan

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018029

Delivery and registration

When is the project declared for completion?

CHINAR CONDOMINIUM is registered with MahaRERA as P52100018029 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018029
Registered on05 Oct 2018
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHINAR CONDOMINIUM record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ganesh Dnyaneshwar Chavan is the promoter of record on 46 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

46projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHINAR CONDOMINIUM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
chinar condominium1G+621 Feb 2021

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for CHINAR CONDOMINIUM, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260183028/03/2026Sushilkumar Shankar Pise vs ganesh dnyaneshwar chavanpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023Due to on going Covid-19 pandemic and lockdown from March 2020 to May 2020 in Maharashtra, Pune and further restrictions after lockdown, there was shortage of construction material

Location, Land & Connectivity

Located at shivajinagar, Gharpure colony, Haveli, Pune, 411005. Per the filed land record, the plot is bounded to the north by Plot no 3, to the south by Plot no 5, to the east by Road and to the west by Police Ground. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shivajinagar

Centropolis
Past its declared completion date · possession by Oct 2026 · Skywards Ashtika Lifestyle
One Place - F C Road
possession by Dec 2026 · Palash Realtors LLP
Buttepatil Capital
possession by Dec 2026 · Buttepatil Properties
Nirmiti Adisha
possession by Dec 2026 · Nirmiti Lifestyle
SAI Chambers
possession by Dec 2026 · Milind Ramkrishna Upasani
Vijay Business Square
possession by Feb 2027 · NS Developers

Other RERA-registered projects in Pune

Chinchechi Baug
declared completion May 2025 · Arun Baban Marathe
Chinmay Avenue
possession by Dec 2027 · Chinmay Avenue
Chinmay Paradise
declared completion Jun 2025 · Chinmay Paradise
Chintamani
declared completion Dec 2017 · Kalyani Vilas
Chintamani
possession by Dec 2027 · Kedar Vikasrao Deshpande
Chintamani Aashish
declared completion Dec 2021 · Rohit Labhade AND Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026