Pune/Project record

MahaRERA · the public record

DEOKATE PARK ROW HOUSE

JALOCHI, BARAMATI · SANDEEP SAMBHAJI DEOKATE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100028332

Delivery and registration

When is the project declared for completion?

DEOKATE PARK ROW HOUSE is registered with MahaRERA as P52100028332 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100028332
Registered on18 Feb 2021
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DEOKATE PARK ROW HOUSE record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sandeep Sambhaji Deokate is the promoter of record on 39 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

39projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DEOKATE PARK ROW HOUSE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
DEOKATE PARK ROW HOUSE A1G+231 Dec 2022
DEOKATE PARK ROW HOUSE B1G+231 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at JALOCHI, BARAMATI, GAT NO 134 (P) , Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by AMENITY SPACE AND OPEN SPACE, to the south by PLOT NO 2, to the east by ADJ GAT NO 172 and to the west by 12 MTR WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baramati

Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon
Adarsh Residency
possession by Oct 2026 · Shivshree Developers
Dream City -A Building
possession by Oct 2026 · Tanaji Sadashiv Pansare
Tanai Heights
possession by Nov 2026 · Surekha Vishnu Kumbhar
Tanai G
possession by Nov 2026 · Surekha Vishnu Kumbhar
Shrivishwa Heights
possession by Dec 2026 · Shrivishwa Developers

Other RERA-registered projects in Pune

Deokate Patils Park Town ROW House C & D
possession by Dec 2027 · Not Available
Deron Bhushanam
declared completion Oct 2020 · Deron Properties PVT LTD
Deron Business Square
declared completion Jun 2021 · Deron Properties PVT LTD
Deshmukh Arcade
possession by Dec 2028 · JAY Deshmukh Construction
Deshmukh Heights
declared completion Dec 2023 · Mauli Builders AND Developers
Deshpande Garden Phase 2
possession by Feb 2028 · Kulshree Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026