Pune/Project record

MahaRERA · the public record

DERON BHUSHANAM

BANER · DERON PROPERTIES PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005409

Delivery and registration

When is the project declared for completion?

DERON BHUSHANAM is registered with MahaRERA as P52100005409 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005409
Registered on11 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for DERON BHUSHANAM record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Deron Properties is the promoter of record on 2 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for DERON BHUSHANAM in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
DERON BHUSHANAM1G+1130 Apr 2019

Legal and disputes

What disputes are disclosed?

9 complaints are on the MahaRERA record for DERON BHUSHANAM, with orders passed in 9 of them.

9complaints

9with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000008547323/04/2021Vishal Prabhakar Maradkar vs M/s Deron Properties Pvt Ltd through its Director Prakash Mokashiorder passed
CC00500000008556219/05/2021Ms. Neha and Mr. Pankaj Guglani vs P52100005409order passed
CC00500000009570501/07/2021Sunita Goswami vs Deron Properties Pvt. Ltd.order passed
CC00500000009573301/07/2021SDA Developers LLP vs Deron Properties Pvt. Ltdorder passed
CC00500000009589227/08/2021Pushpendra Dubey vs Deron Properties Private Limitedorder passed
CC00500000009604022/10/2021ALOK GOVIND MULEY vs DERON PROPERTIES PVT LTDorder passed
CC00500000013716329/05/2022Amit Kirit Mehta vs M/s. Deron Properties Pvt. Ltd.,order passed
CC00500000017785228/11/2022Rahul Kantilal Bhatt vs Deron Properties Pvt Ltd Through Director (Mr.Umang Madan)order passed
CC1250320510/09/2025Akaram Tanaji Bagal vs DERON PROPERTIES PVT LTDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020There was a public interest litigation filed in the Honorable High Court, Mumbai, against issuing permissions for constructions as well as completion certificate. Initially we had

Location, Land & Connectivity

Located at BANER, BANER RD, Haveli, Pune, 411045. Per the filed land record, the plot is bounded to the north by SUS BANER ROAD, to the south by CULVERT ODHA, to the east by S NO 63 2 2 and to the west by S NO 63 2 4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~0 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Baner–Balewadi belt0 km
Hinjewadi Rajiv Gandhi IT Park5 km
Pune Junction / city centre11 km
Pune Int'l Airport (Lohegaon)16 km
Magarpatta / Hadapsar IT17 km
Kharadi / EON IT Park18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Deron Properties PVT LTD is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Deron Properties PVT LTD

Deron Properties PVT LTD
Past its declared completion datePune

Other RERA-registered projects in Baner

1 NEW Castle
possession by Sep 2026 · Chavda Realty LLP
17 East
possession by Sep 2026 · Platinum Properties
Downtown
possession by Sep 2026 · Samarttha Buildcon
Grace Avenue
possession by Sep 2026 · Trimurthy Narayan
Kavish Residency
possession by Sep 2026 · Damle Gandhe LLP
Rahul Altimus
possession by Oct 2026 · Rahul Construction Company

Major developers building in Baner

Other RERA-registered projects in Pune

Deron Business Square
declared completion Jun 2021 · Deron Properties PVT LTD
Deshmukh Arcade
possession by Dec 2028 · JAY Deshmukh Construction
Deshmukh Heights
declared completion Dec 2023 · Mauli Builders AND Developers
Deshpande Garden Phase 2
possession by Feb 2028 · Kulshree Builders
Deshpande Somani Square
possession by Dec 2030 · Somani Landmarks LLP
Destination 12 Gems
possession by Jul 2027 · D R Gavhane Landmarks LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026