MahaRERA Property Intelligence · Pune

Dream Heights

P52100035014 · Shirur · promoter Dream Heights Premises

Certificate SignedDue 31 Mar 2024

Delivery & Registration

MahaRERA registrationP52100035014
Registered on28 Apr 2022
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dream Heights Premises is the promoter of record on 45 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Dream Heights1G+431 Mar 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Shirur, Shirur, Shirur, Pune, 412210. Per the filed land record, the plot is bounded to the north by Adj plot 6, to the south by 12m wide road, to the east by Adj Plot 1148 4 and to the west by Adj plot no 17. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~55 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park55 km
Pune Int'l Airport (Lohegaon)55 km
Magarpatta / Hadapsar IT59 km
Pune Junction / city centre62 km
Baner–Balewadi belt70 km
Hinjewadi Rajiv Gandhi IT Park72 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shirur

Advik Paradise
possession by Aug 2026 · NG Developers
1 Sadabaug Phase-I
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-II
possession by Sep 2026 · Lalita Dharamchand Phulfagar
1 Sadabaug Phase-III
possession by Sep 2026 · Lalita Dharamchand Phulfagar
Babji Market
possession by Sep 2026 · Pyramid Constructions
Rayat Residency
possession by Sep 2026 · Soham Constructions AND Developers

Other RERA-registered projects in Pune

Dream Home Panna
declared completion Jun 2022 · Dream Home Builders
Dream Horizon
possession by Dec 2027 · Moze Properties
Dream MAX
declared completion Dec 2018 · Moze Properties
Dream Park
possession by Dec 2026 · D S Construction
Dream Savera
declared completion Dec 2021 · Moze Properties
Dream Wisteria 1
declared completion Jul 2025 · Adicon Builders AND Promoters Private Li

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026