Plotted Development Intelligence · Pune

DURVA PARK PHASE 1 D

P52100030078 · SASTE NAGAR · promoter Amit Raghunath More

Certificate SignedDue 15 Jun 2022

Delivery & Registration

MahaRERA registrationP52100030078
Registered on29 Jul 2021
Promoter-declared completion15 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Amit Raghunath More is the promoter of record on 50 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at SASTE NAGAR, NEAR SILVER OAK, Khed, Pune, 412105. Per the filed land record, the plot is bounded to the north by BY PROPERTY OF SHRI SASTE KALE HONRAO, to the south by BY REMAINING PROPERTY OF RAJESH GOWDA, to the east by BY PROPERTY OF RAJESH GOWDA and to the west by KHIVSARA AND ASSOCIATES. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt4 km
Hinjewadi Rajiv Gandhi IT Park5 km
Pune Junction / city centre12 km
Pune Int'l Airport (Lohegaon)14 km
Kharadi / EON IT Park17 km
Magarpatta / Hadapsar IT17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Swastik Twin Tower
possession by Jul 2026 · Swastik Builders
Asha Paradise
possession by Jul 2026 · G T Buildcon
Dhrupi Towers
possession by Jul 2026 · Not Available
RKL Durvankur Jaswand
possession by Jul 2026 · Lunkad Vishwa Developer
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Prime Space
possession by Aug 2026 · Nath Estate

Major developers building in Moshi

Other RERA-registered projects in Pune

Durva Park Phase 2 B
declared completion Jun 2022 · Rajesh Eriappa Gowda
Durva Residence
declared completion Dec 2019 · Pradeep Manik Bhise
Durvankur Apartment
declared completion Dec 2018 · Vinayak Developers
Durvankur Residency
declared completion Dec 2023 · JAI Ganesh Construction
Durvankur Residency C Wing
declared completion May 2026 · Durvankur Developers
Durvankur Residency Phase-2
declared completion Jun 2018 · Rajesh Sadhuram Gurnani

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026