Pune/Project record

MahaRERA · the public record

ELLANZA PHASE - B

- · MAHESH VITTHAL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100033777

Delivery and registration

When is the project declared for completion?

ELLANZA PHASE - B is registered with MahaRERA as P52100033777 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100033777
Registered on08 Mar 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ELLANZA PHASE - B record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Mahesh Vitthal is the promoter of record on 74 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

74projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ELLANZA PHASE - B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
ELLANZA PHASE - B1G+2031 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at -, WADGAON BUDRUK, HAVELI, Pune City, Pune, 411041. Per the filed land record, the plot is bounded to the north by S NO 41A, to the south by S NO 41B, to the east by 9 Mtrs WIDE ROAD AND PORTION OF S No 41B and to the west by PROPOSED 24 Mtrs WIDE DP ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahesh Vitthal is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Ellora Enclave
possession by Jul 2028 · Abhirama Properties
Ellora Shopee
possession by Sep 2026 · Ellora Realities Private Limited
Ellwood Homes
declared completion Dec 2023 · Shreeji Group
Elysia
declared completion Dec 2025 · Triaa Eliseo Housing LLP
Elysia Towers
declared completion Jun 2025 · Bhakti Builders
Elysium
declared completion Jun 2024 · Anand Yashwant Buchade

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026