Pune/Project record

MahaRERA · the public record

Friends Heritage

- · Friends Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013597

Delivery and registration

When is the project declared for completion?

Friends Heritage is registered with MahaRERA as P52100013597 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013597
Registered on16 Oct 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Friends Heritage record 19 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Friends Developers is the promoter of record on 19 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

19projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Friends Heritage in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Friends Heritage1G+6-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Oct 2020Due to Non Sale of require flats. We are facing Fund Problem.
30 Oct 202031 Dec 2021Project is completed, due to Covid'19 Possession is delayed.

Location, Land & Connectivity

Located at -, -, Mawal, Pune, 410506. Per the filed land record, the plot is bounded to the north by Gat No 38, to the south by 9 mtr road, to the east by Gat No 38 and to the west by 36 mtr road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~106 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park106 km
Baner–Balewadi belt112 km
Pune Junction / city centre122 km
Pune Int'l Airport (Lohegaon)122 km
Kharadi / EON IT Park125 km
Magarpatta / Hadapsar IT127 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Friends Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Friends Developers project & its RERA track record →

Other RERA-registered projects in Talegaon Dabhade

Vaarivana Phase D - 2A
possession by Oct 2026 · Sanjivani Integrated Township LLP
Rohan Anand Phase II
possession by Dec 2026 · Rohan Builders & Developers Private
Abhimaan Homes Phase 3
possession by Dec 2026 · Rising Propcon LLP
City Plaza
Past its declared completion date · possession by Dec 2026 · Shreenathji Construction LLP
Cradle OF Life Phase 1
possession by Dec 2026 · Gadsing Infra & Hospitality LLP
Greenville
possession by Dec 2026 · Shreeji Developers

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Friends Nook Apartment
possession by Mar 2028 · Icon Constructions
Friendship Residency
declared completion Jan 2024 · Sulabha Dinesh Chaudhari
Fusion Towers Phase II
declared completion Dec 2022 · Rama Synergy Spaces
Fusion Towers Phase III
declared completion Jul 2026 · Rama Synergy Spaces
Fusion Towers Phase IV
possession by Dec 2026 · Rama Synergy Spaces
Future City
declared completion May 2024 · Arihant Reality

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026