MahaRERA · the public record
CITY PLAZA
TALEGAON DABHADE · Shreenathji Construction LLP
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100028180
Delivery and registration
When is the project declared for completion?
CITY PLAZA is registered with MahaRERA as P52100028180 and the promoter has declared completion for 31 Dec 2026.
31 Dec 2026
declared completion
3months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100028180 |
| Registered on | 10 Feb 2021 |
| Promoter-declared completion | 31 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 3 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CITY PLAZA record 19 quarterly progress reports since registration.
19quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Completion date lapsed — the registered completion date has lapsed without a recorded finish.
- Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Shreenathji Construction Llp is the promoter of record on 25 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
25projects
registered with MahaRERA
3flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In CITY PLAZA, ₹8.65 Cr of a declared ₹8.65 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.
100.0%
₹8.65 Cr
of ₹8.65 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In CITY PLAZA, 21 of 63 units filed with MahaRERA are recorded as sold or booked, about 33%, and 42 remain available.
33%sold
21 of 63 units
₹4.76 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹2.99 Cr (about 63%) is recorded as collected and ₹1.77 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 21 registered agreements, the effective carpet rate is ₹8,732/sqft, with eight in ten falling between ₹7,697 and ₹10,689 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.
What the filings record, unit by unit
Read from MahaRERA on 18 July 2026
MahaRERA publishes, unit by unit, what this promoter filed: which units are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific unit. On this project 21 units carry one, and 42 of the 63 are recorded unsold.
Here is one of those unsold units, priced against what buyers of the same unit on other floors actually filed:
| Unit | Carpet | Filed for the same unit on other floors | Based on |
|---|---|---|---|
| F02 | 245 sqft | Rs 19.33 lakh typical, over Rs 15.00 lakh to Rs 23.00 lakh | 8 filed on this stack, floors 2–3 |
A filed consideration is what was registered for one unit. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the unit is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In CITY PLAZA, 33 of the 42 unsold units have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 63 units are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| CITY PLAZA | 1 | G+7 | 63 | - |
Unit mix on the filing: 63 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Dec 2023 | Date-04/02/2023 To, The Maharashtra Real Estate Regulatory Authority, Reference- RERA REGISTRATION NO- P52100028180 Subject: Application for extension of date of completio |
| 30 Dec 2023 | 30 Jun 2024 | Due to Covid 19 pandemic we were not able to construct anymore because of lack of labour contractor and the poor market condition, we were unable to complete the project within the |
| 30 Jun 2024 | 31 Dec 2026 | 1. Project Details That we are the promoters/partners of the project namely “City Plaza”, registered with Maharashtra Real Estate Regulatory Authority under Registration No. P52100 |
Location, Land & Connectivity
Located at TALEGAON DABHADE, 912/2, 913/3 PLOT NO. A-2 AND A-3, SAMSON NAGAR NEXT TO BANK OF MAHARASHTRA, NEAR TALEGAON DABHADE RAILWAY STATION, TALEGAON DABHADE, TAL.- MAWAL, DIST. PUNE, Mawal, Pune, 410506. Per the filed land record, the plot is bounded to the north by 18 MT COLONY ROAD, to the south by PLOT NO A-5 AND OPEN SPACE, to the east by PLOT NO A-4 and to the west by PLOT NO A-1. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| Hinjewadi Rajiv Gandhi IT Park | 17 km |
| Baner–Balewadi belt | 22 km |
| Pune Int'l Airport (Lohegaon) | 31 km |
| Pune Junction / city centre | 31 km |
| Kharadi / EON IT Park | 35 km |
| Magarpatta / Hadapsar IT | 36 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.