147units filed as unsoldInventory · 17 September 2026
30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
379registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100023186

Delivery and registration

When is the project declared for completion?

ROHAN ANAND PHASE I is registered with MahaRERA as P52100023186 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100023186
Registered on05 Dec 2019
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROHAN ANAND PHASE I record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rohan is the promoter of record on 82 projects registered with MahaRERA, 7 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

82projects

registered with MahaRERA

7flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In ROHAN ANAND PHASE I, ₹42.81 Cr of a declared ₹34.21 Cr estimated project cost is reported as incurred, about 125.1%, as at the last certified filing with MahaRERA.

125.1%

₹42.81 Cr

of ₹34.21 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In ROHAN ANAND PHASE I, 232 of 379 homes filed with MahaRERA are recorded as sold or booked (231 with registered agreements and 1 booked), about 61%, and 147 remain available.

61%sold

232 of 379 homes

₹45.32 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹41.86 Cr (about 92%) is recorded as collected and ₹3.45 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 232 registered agreements, the effective carpet rate is ₹5,712/sqft, with eight in ten falling between ₹5,613 and ₹5,960 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 232 homes carry one, and 147 of the 379 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
C-209538 sqftRs 5,935 a sq ft typical, over Rs 5,358 to Rs 7,17750 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In ROHAN ANAND PHASE I, 132 of the 147 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 146 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 379 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building C1G+1211031 Dec 2023
Building D1G+1213131 Dec 2023
Building E1G+1213831 Dec 2023

Unit mix on the filing: 379 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ROHAN ANAND PHASE I, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
SM1260009623/01/2026Ram Gawali vs ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITEDorder passed

Location, Land & Connectivity

Located at Somatane, Somatane Phata Road, Pune City, Pune, 410506. Per the filed land record, the plot is bounded to the north by ADJ GAT NO 109, to the south by Road, to the east by ADJ GAT NO 115 and 116 and to the west by ADJ GAT NO 112 Part and 110 Part. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park14 km
Baner–Balewadi belt19 km
Pune Junction / city centre29 km
Pune Int'l Airport (Lohegaon)29 km
Kharadi / EON IT Park33 km
Magarpatta / Hadapsar IT34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rohan Builders & Developers Private Limited is the promoter on 28 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Rohan Builders & Developers Private Limit project & its RERA track record →

Other flagged projects by Rohan Builders & Developers Private Limit

Rohan Builders & Developers Private Limited
FlaggedPune
Rohan Builders & Developers Private Limited
FlaggedPune
Rohan Builders & Developers Private Limited
FlaggedPune
Rohan Builders & Developers Private Limited
FlaggedPune
Rohan Builders & Developers Private Limited
FlaggedPune
Rohan Builders & Developers Private Limited
FlaggedPune

Other RERA-registered projects in Talegaon Dabhade

Vaarivana Phase D - 2A
possession by Oct 2026 · Sanjivani Integrated Township LLP
Rohan Anand Phase II
possession by Dec 2026 · Rohan Builders & Developers Private
Abhimaan Homes Phase 3
possession by Dec 2026 · Rising Propcon LLP
City Plaza
Past its declared completion date · possession by Dec 2026 · Shreenathji Construction LLP
Cradle OF Life Phase 1
possession by Dec 2026 · Gadsing Infra & Hospitality LLP
Greenville
possession by Dec 2026 · Shreeji Developers

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Rohan Anand Phase II
possession by Dec 2026 · Rohan Builders & Developers Private
Rohan Ananta Phase II
declared completion Mar 2025 · Rohan Builders & Developers Private
Rohan Ananta Phase III
declared completion Mar 2026 · Rohan Builders & Developers Private
Rohan Ananya
declared completion Dec 2025 · Rohan & Atul Enterprises
Rohan Ekam Phase 1
possession by Dec 2027 · Rohan Builders & Developers Private
Rohan Ekam Phase 2
possession by Mar 2030 · Rohan Builders & Developers Private

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026