Pune/Project record

MahaRERA · the public record

CITY VISTA

Kharadi · KOLTE-PATIL REAL ESTATE PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100007612

Delivery and registration

When is the project declared for completion?

CITY VISTA is registered with MahaRERA as P52100007612 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100007612
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CITY VISTA record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kolte-Patil is the promoter of record on 91 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

91projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CITY VISTA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
B FLOOR 1 TO 71G+1031 Dec 2019
B FLOOR 8 TO 9 and Ground Floor ATM1G+231 Dec 2019

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for CITY VISTA, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001103301/03/2018NAYAN NANASAHEB GANDHI vs M/s Kolte Patil Estate Private Limitedorder passed
CC00500000001110301/03/2018NAYAN NANASAHEB GANDHI vs M/s Kolte Patil Real Estate Private Limitedorder passed
CC00500000002331923/08/2019Satyendra Seth vs Rajesh Patilorder passed

Legal & Litigation

The promoter has declared 10 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd Pune1315/20082008Issues
Cjsd Pune852/20122012Issues
Cjsd Pune930/20142014Awaiting Summons Or Hearing On Interim Application
Cjsd Pune563/20172017For Issues
Cjsd Pune1044/20172017For Issues
District Court Pune385/20172017For Filing Of Say
District Court402/20172017For Filing Of Say
Cjsd Pune828/20182018For Written Statement
Cjsd Pune1153/20182018Arguments On Interim Application
Cjsd PuneSPL CS 1169/20182018Apperance

Location, Land & Connectivity

Located at Kharadi, Nagar Road , Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by 9 MTR WIDE FRONT MARGIN OF LAYOUT, to the south by A BUILDING, to the east by 36 MTR WIDE DP ROAD and to the west by OPEN SPACE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Kharadi / EON IT Park1 km
Pune Int'l Airport (Lohegaon)4 km
Magarpatta / Hadapsar IT6 km
Pune Junction / city centre8 km
Baner–Balewadi belt18 km
Hinjewadi Rajiv Gandhi IT Park22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Kolte-Patil Real Estate Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Kolte-Patil Real Estate Private Limited project & its RERA track record →

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Civcon Residency
declared completion Aug 2025 · Archway Properties
Classic Amrut
possession by Oct 2026 · Classic Infra
Classic Exotica B
declared completion Dec 2022 · Classic Developers
Classic Gloria Building B
declared completion Mar 2026 · Classic Properties
Classic Icon
declared completion Sep 2021 · Shamrao Sukhadeo Patil
Classic Niyati
declared completion Dec 2017 · Classic Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026