Pune/Project record

MahaRERA · the public record

GANGA SERIO E F BUILDING

KHARADI · GOEL GANGA LANDMARKS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100023713

Delivery and registration

When is the project declared for completion?

GANGA SERIO E F BUILDING is registered with MahaRERA as P52100023713 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100023713
Registered on02 Jan 2020
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GANGA SERIO E F BUILDING record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for GANGA SERIO E F BUILDING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28.

BuildingWingsFloorsDeclared completion
E1G+28-
F1G+28-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for GANGA SERIO E F BUILDING, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250092217/03/2025Sachinkumar Prabhakar Sahu vs GOEL GANGA LANDMARKS LLPorder passed
CC1250138125/04/2025Savita Sharma vs GOEL GANGA LANDMARKS LLPorder passed

Location, Land & Connectivity

Located at KHARADI, KHARADI, Pune City, Pune, 411014. Per the filed land record, the plot is bounded to the north by Adj S No 17, to the south by Adj S No P2, to the east by Adj S No P5C and to the west by 18M WIDE INTERNAL ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~159 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)158 km
Kharadi / EON IT Park159 km
Magarpatta / Hadapsar IT162 km
Pune Junction / city centre166 km
Baner–Balewadi belt172 km
Hinjewadi Rajiv Gandhi IT Park174 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Goel Ganga Landmarks LLP is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Goel Ganga Landmarks LLP

Goel Ganga Landmarks LLP
FlaggedPune
Goel Ganga Landmarks LLP
FlaggedPune

Other RERA-registered projects in Kharadi

Satyam Shivam Phase 2
Not filing quarterly progress reports · possession by Sep 2026 · Vijayalaxmi Associates
The Collection - W2 And W7
possession by Sep 2026 · Bramhacorp Limited
Unique Youtopia Phase III
possession by Sep 2026 · Unique Associates
Spandan
possession by Oct 2026 · Evolve Infra
Ganga Platinum A
possession by Oct 2026 · Shree Balaji Associates Pune LLP
Percept Bounty 3
possession by Dec 2026 · Prime Estate

Major developers building in Kharadi

Other RERA-registered projects in Pune

Ganga Serio G Building
declared completion Dec 2025 · Goel Ganga Landmarks LLP
Ganga Sierra
possession by Dec 2026 · Ganraj Infrastructure LLP
Ganga Trinity Phase I A1a2a3
declared completion Dec 2025 · Ganraj Infrastructure LLP
Ganga Trueno Tower B
declared completion Dec 2022 · Kappa Realtors LLP
Ganga Utopia Commercial
possession by Dec 2026 · Goel Ganga Developments LLP
Ganga Utopia E Building
possession by Dec 2026 · Goel Ganga Developments LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026