GAURAMI SQUARE

Dudulgaon · SDS CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

46units filed as unsoldInventory · 20 September 2026
30 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
51registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100077704

Delivery and registration

When is the project declared for completion?

GAURAMI SQUARE is registered with MahaRERA as P52100077704 and the promoter has declared completion for 30 Jun 2028.

30 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100077704
Registered on22 Oct 2024
Promoter-declared completion30 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for GAURAMI SQUARE record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In GAURAMI SQUARE, ₹7.94 Cr of a declared ₹15.63 Cr estimated project cost is reported as incurred, about 50.8%, as at the last certified filing with MahaRERA.

50.8%

₹7.94 Cr

of ₹15.63 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In GAURAMI SQUARE, 5 of 51 homes filed with MahaRERA are recorded as sold or booked, about 10%, and 46 remain available.

10%sold

5 of 51 homes

₹2.17 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹33.35 Lakh (about 15%) is recorded as collected and ₹1.84 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 5 registered agreements, the effective carpet rate is ₹7,640/sqft, with eight in ten falling between ₹7,230 and ₹7,640 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 5 homes carry one, and 46 of the 51 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
604565 sqftRs 43.15 lakh typical, over Rs 42.80 lakh to Rs 43.15 lakh4 filed on this stack, floors 2–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In GAURAMI SQUARE, 17 of the 46 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 45 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 51 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A1G+751-

Unit mix on the filing: 25 residential and 26 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Dudulgaon, Near PCMC School, Mulshi, Pune, 412105. Per the filed land record, the plot is bounded to the north by 18 Mtrs Road, to the south by Property of Kurhade of Gat no 161, to the east by Property of Mungse and 18 Mtrs Road and to the west by Remaining property of Gat No 161. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Int'l Airport (Lohegaon)11 km
Kharadi / EON IT Park15 km
Pune Junction / city centre16 km
Baner–Balewadi belt17 km
Hinjewadi Rajiv Gandhi IT Park18 km
Magarpatta / Hadapsar IT18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Gaurav Icon Tower
declared completion Mar 2026 · Gaurav Icon Infratech PVT LTD
Gaurav Pride
declared completion Dec 2017 · GRD Infraprojects Private Limited
Gauri Nandan Apartments
possession by Dec 2027 · VC Bace Constrotech LLP
Gaurinandan Heights
possession by Dec 2027 · Trident Civil Projects
Gawade Galore
possession by Mar 2028 · Gawade Lifespace LLP
Gayatrree Grace
declared completion Jan 2018 · Gayatrree Skyscrapers India LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026