MahaRERA Property Intelligence · Pune

INDO HOMES

P52100025562 · MAHATMA PHULE PETH · promoter Indo Construction And

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP52100025562
Registered on28 Jun 2020
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Indo Construction And is the promoter of record on 19 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
INDO HOMES1G+631 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MAHATMA PHULE PETH, 367/B, Pune City, Pune, 411042. Per the filed land record, the plot is bounded to the north by SNO367B PART, to the south by ROAD, to the east by SNO367B and to the west by SNO367A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghorpade Peth

Sanghvi Premio
possession by Oct 2026 · Nitin Kantilal Sanghvi
Samaira Tower
possession by Nov 2026 · Prathamesh Constro Realty Llp
Shri Balaji Sudarshan
Deregistered by MahaRERA · possession by Dec 2026 · Shri Balaji Sudarshan
Radiance
Not filing quarterly progress reports · possession by Dec 2026 · Mohammed Sabir Husain Shaikh
Shree Swami Krupa Sadan
possession by Dec 2026 · A S Associates
Siddhi Plaza
possession by Dec 2026 · Shree Developers

Major developers building in Ghorpade Peth

Other RERA-registered projects in Pune

Indra Praniti Co-Operative Housing Society
possession by Dec 2028 · M/s. Fortune Developers
Indraa Park
declared completion Dec 2021 · S K Buildcon
Indradhanu Residency
declared completion Jun 2019 · A Team Associates
Indralok Nagari
declared completion Apr 2024 · Yavat Realty
Indraprasth
possession by Dec 2026 · J V Buildcon
Indraprastha
declared completion Feb 2021 · Omkar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026