KALA GOLD

Pune · SHRI BALAJI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2017declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100014248

Delivery and registration

When is the project declared for completion?

KALA GOLD is registered with MahaRERA as P52100014248 and the promoter has declared completion for 31 Dec 2017.

31 Dec 2017

declared completion

105months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100014248
Registered on16 Nov 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 105 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KALA GOLD record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KALA GOLD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
KALA GOLD1G+8-

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for KALA GOLD, with orders passed in 4 of them.

4complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000002218125/10/2018Bijay Kumar Singh vs Mr. Hanumant Arjun Harpale, Khandu Dashrath Gangane, Deepak Uttam Jawanjal & Sagar Balasaheb Dhoreorder passed
CC00500000002226820/11/2018TANAJI SHINDE vs SHRI BALAJI DEVLOPERSorder passed
CC00500000005388905/01/2020Mr. Nimba Sukdev Damre vs M/s. Balaji Developers Through its Partner Mr. Hanumant Arjun Harpaleorder passed
CC00500000005391812/01/2020Mr. Rajendra Dadabhau Kedare vs Shree Balaji Developers through its Partner Mr. Deepak Uttam Jawanjalorder passed

Location, Land & Connectivity

Located at Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by MORGAON - JEJURI ROAD, to the south by GAT NO 162, to the east by GAT NO 164 and to the west by GAT NO 162. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~103 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park103 km
Baner–Balewadi belt109 km
Pune Junction / city centre119 km
Pune Int'l Airport (Lohegaon)120 km
Kharadi / EON IT Park123 km
Magarpatta / Hadapsar IT124 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shri Balaji Developers is the promoter on 6 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shri Balaji Developers

Shri Balaji Developers
FlaggedPune

Other RERA-registered projects in Fursungi

Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
THE Mpire Building E
possession by Dec 2026 · AGN Venture
Vandan Vihar
possession by Jun 2027 · GVN Developers PVT LTD
AGS Complex
possession by Sep 2027 · AGS Properties
Pacific Tower
possession by Sep 2027 · Chaitanya Developers

Major developers building in Fursungi

Other RERA-registered projects in Pune

Kala Kamal Park
declared completion Dec 2019 · Khodade Borhade Properties
Kalakunj CD
declared completion Oct 2025 · VG Empires LLP
Kalash Apartment
declared completion Dec 2019 · P R Builders Anddevelopers
Kalash Ganga
declared completion Mar 2025 · Abhijit Shivaji Marne
Kalash Phase 2 Wing A AND B
declared completion Jul 2019 · Kalyanee Fortune Properties
Kalash Residency
possession by Mar 2028 · Pramod Ramdas Bangar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026