Plotted Development Intelligence · Pune

KASHIVISHVESHWAR PARK

P52100032491 · BARAMATI · promoter Shivtej Developers

Certificate SignedDue 23 Jul 2025

Delivery & Registration

MahaRERA registrationP52100032491
Registered on10 Jan 2022
Promoter-declared completion23 Jul 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shivtej Developers is the promoter of record on 6 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BARAMATI, MALEGAON ROAD, KHANDOBA NAGAR, Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by CTS NO 128 1 4, to the south by CTS NO 126, to the east by CTS NO 128 B TAWARE LAND and to the west by 128 1 B 2 B 2 REMAINING SUBHASH DHUMAL LAND. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Baramati

Nirvana Elite
possession by Jul 2026 · Akash Jayesh Associates
Sharada Baug
possession by Aug 2026 · Mandar Shrikant Sikachi
G G Capital
possession by Aug 2026 · GG Builders AND Developers
Mayureshwar Icon
possession by Sep 2026 · Mayureshwar Reality AND Developers
Gadhavenanaware Heights
possession by Sep 2026 · Shri Developers
Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon

Major developers building in Baramati

Other RERA-registered projects in Pune

Kashmira Ela
declared completion Mar 2023 · Ashwini R Deshmukh
Kasturi
declared completion Dec 2022 · Nakshatra Buildcon
Kasturi
declared completion Jul 2024 · B K Associate
Kasturi
declared completion Jun 2024 · Morya Landmarks
Kasturi
possession by Dec 2028 · Adi Developers
Kasturi Apt
declared completion May 2018 · Shruti Shripad Kulkarni

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026