LAXMI PARADISE

ALANDI MHATOBA · THE LAXMI EMPIRE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

344units filed as unsoldInventory · 19 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100054082

Delivery and registration

When is the project declared for completion?

LAXMI PARADISE is registered with MahaRERA as P52100054082 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100054082
Registered on27 Dec 2023
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for LAXMI PARADISE record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

The Laxmi Empire is the promoter of record on 89 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

89projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In LAXMI PARADISE, 24 of 368 plots filed with MahaRERA are recorded as sold or booked, about 7%, and 344 remain available.

7%sold

24 of 368 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What the filings record, plot by plot

Read from MahaRERA on 19 September 2026

MahaRERA publishes, plot by plot, what this promoter filed: which plots are sold and which are not, the filed area of each, and for the sold ones the registered agreement value — the consideration filed for that specific plot. On this project 24 plots carry one, and 344 of the 368 are recorded unsold.

Here is one of those unsold plots, priced against what buyers of comparable plots on the same filing actually filed:

PlotAreaFiled for comparable plots on the same filingBased on
Plot No 241,243 sqftRs 1,176 a sq ft typical, over Rs 772 to Rs 1,96112 filed at this size

A filed consideration is what was registered for one plot. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the plot is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In LAXMI PARADISE, 281 of the 344 unsold plots have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 343 plots — ₹2,999 →

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for LAXMI PARADISE, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250176729/05/2025Hajilal Shabbir Shaikh vs THE LAXMI EMPIREpending / no order on file

Legal & Litigation

The promoter has declared 6 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your plot. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Pune MaharashtraSpl. C. S. No. 327/20242024Ongoing
Civil Court Pune MaharashtraSpl.C.S./1060/20242024Ongoing
In The High Court Of Judicature At Bombay Civil Appellate JurisdictionCRA/262/20242024Ongoing
In The High Court Of Judicature At Bombay Civil Appellate JurisdictionAO/431/20242024Ongoing
In The High Court Of Judicature At Bombay Civil Appellate JurisdictionAO/407/20242024Ongoing
In The High Court Of Judicature At Bombay Civil Appellate JurisdictionAO/299/20252025Ongoing

Location, Land & Connectivity

Located at ALANDI MHATOBA, ALANDI MHATOBA, Haveli, Pune, 412201. Per the filed land record, the plot is bounded to the north by MR SHIVARKAR PROPERTY, to the south by MR JAWALKAR PROPERTY, to the east by SURBHAUGVASTI and to the west by ANIMAL FOREST. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Magarpatta / Hadapsar IT16 km
Kharadi / EON IT Park17 km
Pune Int'l Airport (Lohegaon)21 km
Pune Junction / city centre22 km
Baner–Balewadi belt32 km
Hinjewadi Rajiv Gandhi IT Park38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Loni Kalbhor

Arvan Residency
possession by Dec 2026 · Sanskruti Developers
Keshavyog Residency
possession by Dec 2026 · Siddhivinayak Builders
Muktai Park Phase II
possession by Dec 2026 · Shivshakti Buildcon
Platinum Nirvana
possession by Dec 2026 · Platinum Developers
Swami Homes
possession by Jan 2027 · S S Developers
Krishnai Residency
possession by Mar 2027 · Ivana Properties

Other RERA-registered projects in Pune

Laxmi Pride
declared completion Jun 2025 · M/S B J Hulawale Properties
Laxmi Puram
possession by Sep 2027 · Not Available
Laxmi Residency
declared completion Sep 2023 · Nanda Manjule
Laxmi Shrushti
possession by Mar 2028 · Shrushti Developers
Laxmi Vihar
possession by Dec 2029 · Laxmi Buildcon
Laxmi Vihar A And B Building
possession by Dec 2027 · V S Kalbhor AND Company

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026