Pune/Project record

MahaRERA · the public record

MAHALAXMI ICON

Pimprigaon · Shree Swami Samarth Buildcon

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jan 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jan 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100015313

Delivery and registration

When is the project declared for completion?

MAHALAXMI ICON is registered with MahaRERA as P52100015313 and the promoter has declared completion for 30 Jan 2022.

30 Jan 2022

declared completion

56months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100015313
Registered on15 Feb 2018
Promoter-declared completion30 Jan 2022
Current statusCertificate Signed
Against todayabout 56 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAHALAXMI ICON record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAHALAXMI ICON in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
MAHALAXMI ICON1G+631 Jan 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Pimprigaon, CTS-537, 539, 539/1, 539/8, 539/9, Near Pavana Sahakari Bank, Haveli, Pune, 411017. Per the filed land record, the plot is bounded to the north by Temple and Road, to the south by CTS No-534, to the east by Plot of Bhausaheb G Waghere and to the west by CTS No-536 And Part of 537. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Baner–Balewadi belt6 km
Pune Junction / city centre9 km
Hinjewadi Rajiv Gandhi IT Park11 km
Magarpatta / Hadapsar IT14 km
Pune Int'l Airport (Lohegaon)16 km
Kharadi / EON IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Swami Samarth Buildcon is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shree Swami Samarth Buildcon project & its RERA track record →

Other RERA-registered projects in Rahatani

Devkamal Heights
possession by Oct 2026 · MRS Kamal Devram Hole
KK Mangalam Emerald
possession by Oct 2026 · Shah Associates & Properties
AUM Vertex
possession by Dec 2026 · Aum Buildcon
KK Capitol
possession by Dec 2026 · Shah AND Associates
Tamara
possession by Dec 2026 · Goldfinger Kataria Urban Developments
Aurelia
possession by Dec 2026 · Shitole Properties

Major developers building in Rahatani

Other RERA-registered projects in Pune

Mahalaxmi Icon
declared completion Oct 2025 · Akash Developers
Mahalunge Riviera A1 Bldg
declared completion May 2026 · J And J Associates
Mahalunge Riviera C Wing
possession by Mar 2029 · J AND J Associates
Maharaja
declared completion Dec 2025 · Kalyani Amol Infra LLP
Mahaveer Darshan
declared completion Dec 2024 · Yashodhan Associates
Mahaveer Delight
declared completion Dec 2017 · Yashodhan Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026