MORESHWAR RESIDENCY

TALUKA HAVELI · S K DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 12 September 2026
30 Sep 2024declared completionMahaRERA registration · read 12 Jul 2026
32registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100018253

Delivery and registration

When is the project declared for completion?

MORESHWAR RESIDENCY is registered with MahaRERA as P52100018253 and the promoter has declared completion for 30 Sep 2024.

30 Sep 2024

declared completion

24months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100018253
Registered on16 Oct 2018
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MORESHWAR RESIDENCY record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Sales

How much has actually been sold?

In MORESHWAR RESIDENCY, 23 of 23 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

23 of 23 homes

₹4.76 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹4.58 Cr (about 96%) is recorded as collected and ₹17.68 Lakh as receivable. The project registers 32 homes in total, while this sold/unsold inventory filing covers 23 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 23 registered agreements, the effective carpet rate is ₹4,489/sqft, with eight in ten falling between ₹4,074 and ₹4,801 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 9 not for sale.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 23 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Every home in MORESHWAR RESIDENCY is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 23 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 23 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 32 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
A WING1G+51431 Mar 2022
B WING1G+5631 Mar 2022
C WING1G+51231 Mar 2022

Unit mix on the filing: 30 residential and 2 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at TALUKA HAVELI, WADKI, Haveli, Pune, 412308. Per the filed land record, the plot is bounded to the north by PROPERTY OF WIDE ROAD 9 MTR, to the south by GAT NO 477, to the east by GAT NO 478 and to the west by PROPERTY OF GAT NO 479. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

S K Developers is the promoter on 18 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by S K Developers

S K Developers
Past its declared completion datePune

Other RERA-registered projects in Fursungi

Casalino Towers Phase 3
possession by Oct 2026 · Sai Siddhi Promoters & Builders
Green Hive Plus Wing A4
possession by Dec 2026 · Ram India Shelters
THE Mpire Building E
possession by Dec 2026 · AGN Venture
Vandan Vihar
possession by Jun 2027 · GVN Developers PVT LTD
AGS Complex
possession by Sep 2027 · AGS Properties
Pacific Tower
possession by Sep 2027 · Chaitanya Developers

Major developers building in Fursungi

Other RERA-registered projects in Pune

Morya Alphanso
declared completion Jun 2023 · Morya Developers
Morya Apartment
declared completion Jun 2024 · JAY Sadguru Builders & Developers
Morya City B
declared completion Oct 2023 · Bhagavat Dashrath More
Morya Hills
declared completion Oct 2020 · Ramesh Babanrao Gavhane
Morya ONE
declared completion Dec 2022 · Shree Chintamani Construction
Morya ONE Hospital Project
declared completion Dec 2023 · Shree Chintamani Construction

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.