MahaRERA Property Intelligence · Pune

Nexus Imperia

P52100053378 · Borhadewadi · promoter Sereno Constrotech Llp

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP52100053378
Registered on27 Oct 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sereno Constrotech Llp is the promoter of record on 8 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~6.3% of the estimated project cost incurred as of the last certificate (₹1.16 Cr spent against a ₹18.38 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 84 homes filed with MahaRERA, 54 are sold/booked and 30 remain available (~64% sold) — selling steadily. Buyers have committed ₹15.96 Cr in agreement value so far. Of that, ₹1.17 Cr (~7%) is already collected, ₹14.79 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 54 registered agreements, the effective carpet rate is ₹5,360/sqft (typical range ₹5,360–₹7,874) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101510 sqft (47.41 sqm)₹28.53 Lakh
Floor 1101524 sqft (48.67 sqm)₹29.36 Lakh
Floor 1102692 sqft (64.25 sqm)₹40.24 Lakh
Floor 1102524 sqft (48.67 sqm)₹29.37 Lakh
Floor 1103485 sqft (45.1 sqm)₹27.10 Lakh
Floor 1103505 sqft (46.9 sqm)₹28.22 Lakh
Floor 1104485 sqft (45.1 sqm)₹27.06 Lakh
Floor 1104505 sqft (46.9 sqm)₹28.22 Lakh
Floor 2202692 sqft (64.25 sqm)₹40.24 Lakh
Floor 2203485 sqft (45.1 sqm)₹27.10 Lakh
Floor 2204485 sqft (45.1 sqm)₹27.06 Lakh
Floor 2204505 sqft (46.9 sqm)₹28.22 Lakh
Floor 2205471 sqft (43.72 sqm)₹26.39 Lakh
Floor 3302692 sqft (64.25 sqm)₹40.24 Lakh
Floor 3303485 sqft (45.1 sqm)₹27.10 Lakh
Floor 3303505 sqft (46.9 sqm)₹28.22 Lakh
Floor 3304505 sqft (46.9 sqm)₹28.22 Lakh
Floor 4401510 sqft (47.41 sqm)₹27.35 Lakh
Floor 4402692 sqft (64.25 sqm)₹40.24 Lakh
Floor 4403485 sqft (45.1 sqm)₹27.10 Lakh
Floor 4406510 sqft (47.41 sqm)₹27.35 Lakh
Floor 5502692 sqft (64.25 sqm)₹40.24 Lakh
Floor 6602692 sqft (64.25 sqm)₹40.24 Lakh
Floor 6603485 sqft (45.1 sqm)₹27.10 Lakh
Floor 6606510 sqft (47.41 sqm)₹28.53 Lakh
Floor 7702692 sqft (64.25 sqm)₹40.24 Lakh
Floor 7703485 sqft (45.1 sqm)₹27.10 Lakh
Floor 7704485 sqft (45.1 sqm)₹27.06 Lakh
Floor 7704505 sqft (46.9 sqm)₹27.06 Lakh
Floor 7705471 sqft (43.72 sqm)₹26.39 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 42 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Nexus Imperia2G+842-

Unit mix on the filing: 84 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202631 Dec 2027We are applying for a project extension until 31/12/2027 because we will be applying for corrections in the future.

Location, Land & Connectivity

Located at Borhadewadi , Gat No 79 , Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by Remaining Land Of Gat No 79, to the south by Prop of Mr Surywanshi and PL No 141 A 2 PL NO 35, to the east by Road and to the west by Plot No 142K of PCNTDA. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Swastik Twin Tower
possession by Jul 2026 · Swastik Builders
Asha Paradise
possession by Jul 2026 · G T Buildcon
Dhrupi Towers
possession by Jul 2026 · Not Available
RKL Durvankur Jaswand
possession by Jul 2026 · Lunkad Vishwa Developer
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Prime Space
possession by Aug 2026 · Nath Estate

Major developers building in Moshi

Other RERA-registered projects in Pune

Nexus Kinaara A
possession by Apr 2028 · Nexus Enterprises
Nexus Kinaara B C
declared completion Aug 2025 · Nexus Enterprises
Nexus Kinaara D
declared completion Dec 2025 · Nexus Enterprises
Nexus Meridian
declared completion Jan 2020 · Nexus Infra
Nexus Primesquare
possession by Jun 2027 · Nexus Developers
Nexus Skydale
possession by Dec 2027 · Nexus Infrastructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026