Pune/Project record

MahaRERA · the public record

PADMANABH PHASE 1

Pune · KHUSHANAI DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005786

Delivery and registration

When is the project declared for completion?

PADMANABH PHASE 1 is registered with MahaRERA as P52100005786 and the promoter has declared completion for 30 Sep 2022.

30 Sep 2022

declared completion

48months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005786
Registered on14 Aug 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PADMANABH PHASE 1 record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PADMANABH PHASE 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
Building A11G+10-
Building B21G+9-
Building B11G+9-
Club House1G+1-

Legal and disputes

What disputes are disclosed?

21 complaints are on the MahaRERA record for PADMANABH PHASE 1, with orders passed in 21 of them.

21complaints

21with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001140103/06/2018Akshay Nitin Vaidya vs Sudhir Darodeorder passed
CC00500000000017908/09/2017Pravin Hiwale vs Darode Jog Homes Pvt Ltdorder passed
CC00500000000036219/04/2018Pushkar Brahme vs Anand Dhundiraj Jogorder passed
CC00500000000036904/11/2017Kavita Rasal vs Darode Jog Homes Pvt Ltdorder passed
CC00500000001051708/11/2017Sukrut Rajmane vs Darode Jog Homes Pvt Ltdorder passed
CC00500000001091401/02/2018Vrushal Balkrishna Salunke vs Mr. Sudhir Darode and Mr.Anand Jogorder passed
CC00500000001079804/02/2018Prashant Patil vs Anand Jogorder passed
CC00500000001099228/01/2018SMITA SAHASRABUDHE vs DARODEJOG HOMES PVT LTDorder passed
CC00500000002217023/10/2018Daulatrao Bhagwanrao Raut vs DARODE JOG HOMES PVT LTDorder passed
CC00500000001143718/04/2018DHANAJI GULAB PENDAVALE vs DARODE JOG HOMES PVT. LTD.order passed
CC00500000001144519/04/2018PRAVIN LAXMAN ALIBAGKAR vs SUDHIR DARODE/ANANAD JOGorder passed
CC00500000001145624/04/2018Vaishali Kulkarni vs Sudhir Darode and Anand Jogorder passed
CC00500000001191621/08/2018Pratyush Singh vs MR SUDHIR DARODE & ANAND JOGorder passed
CC00500000002280722/03/2019AJAY SUBHASH TOPALE vs DARODE JOG HOMES PVT LTDorder passed
CC00500000002300422/06/2019AMIT KANTAK &SAILI KANTAK vs Darode Jog Homes Pvt Ltdorder passed
CC00500000003354519/10/2019Ashwini Subhash Kulkarni vs Darode Jog Homes Private Limitedorder passed
CC00500000005420028/10/2020anand mahajan vs Parshuram Kurhade, Anand Jog, Sudhir Darodeorder passed
CC00500000006432512/07/2020MILIND PRAMOD KULKARNI vs SUSHIR DARODEorder passed
CC00500000016733914/07/2022Pitambar Sadashiv Gambare vs Dardode Jog Homes Pvt Ltdorder passed
CC00500000022839325/02/2023ANUJA ASHOK DEOKAR vs DARODE JOG HOMES PRIVATE LIMITEDorder passed
CC00500000027985903/04/2024Mangesh Kadam vs Darode Jog Homes Private Limitedorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Cjsd Pune1231/20162016Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2022covid

Location, Land & Connectivity

Located at Haveli, Pune, 412105. Per the filed land record, the plot is bounded to the north by Gat NO 175, to the south by By Gat No 179, to the east by By 18 mtrs Road and to the west by By Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~118 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park118 km
Baner–Balewadi belt124 km
Pune Junction / city centre134 km
Pune Int'l Airport (Lohegaon)135 km
Kharadi / EON IT Park138 km
Magarpatta / Hadapsar IT139 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Moshi

Ideal Avenue
possession by Sep 2026 · Ideal Builders
Fortune Vedas Phase II
Not filing quarterly progress reports · possession by Sep 2026 · Fortune Vastusilpa Developers LLP
Gulmohar 24
possession by Sep 2026 · Royal Gulmohar Reality
Krishnai Residency
possession by Sep 2026 · Vastu Buildcon
Omkar Residency
possession by Sep 2026 · Prerna Group
Town Square
possession by Sep 2026 · Krupasindhu Developers

Major developers building in Moshi

Other RERA-registered projects in Pune

Padmanabh Phase II
declared completion Dec 2021 · Darode JOG Homes PVT LTD
Padmarang
possession by Mar 2027 · SBS Prroperties
Padmashree Phase - I
possession by Dec 2027 · Nilesh Shashikant Ostwal
Padmavati Angan
possession by Mar 2027 · Samarth Construction & Developers
Padmavati Avenue
possession by Dec 2027 · Jawalkar Realties
Padmavati Dhara Society B-Type
declared completion Dec 2022 · Unique Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026