PALAASH SADAPHULI PHASE 2 A1 WING

Varale · GS ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100005853

Delivery and registration

When is the project declared for completion?

PALAASH SADAPHULI PHASE 2 A1 WING is registered with MahaRERA as P52100005853 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100005853
Registered on14 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PALAASH SADAPHULI PHASE 2 A1 WING record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PALAASH SADAPHULI PHASE 2 A1 WING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
A11G+1230 Jun 2024

Legal and disputes

What disputes are disclosed?

20 complaints are on the MahaRERA record for PALAASH SADAPHULI PHASE 2 A1 WING, with orders passed in 20 of them.

20complaints

20with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00500000001061201/12/2017Rahul Rajput vs D S KULKARNI & COMPANYorder passed
CC00500000001092121/01/2018Kulkarni Jyoti Atul vs D. S. Kulkarni & Companyorder passed
CC00500000001095803/02/2018Hitesh Marotrao Thanekar vs DSKULKARNIANDCOMPANYorder passed
CC00500000001157325/05/2018MANGESH MUKUND KULKARNI vs D S KULKARNI & COMPANYorder passed
CC00500000001169202/07/2018Sumit A Choudhary, Shweta Chndrashekhar Jain vs D.S. Kulkarni & Companyorder passed
CC00500000001171609/07/2018Vinit Babasaheb Lote vs M/s DSK Worldman Projects Ltd.order passed
CC00500000002329331/07/2019Pradeep Wandrekar Chairman of Sadaphuli A, A1 & B CHS Ltd. (society) vs D S Kulkarni and Companyorder passed
CC00500000002207928/09/2018SHIRISH DAPTARDAR vs M/S D S KULKARNI & COMPANYorder passed
CC00500000002219403/11/2018Shirish Digambar Daptardar vs D S Kulkarni & Companyorder passed
CC00500000002209203/10/2018Nitin Suresh Jain vs DSK Worldman Projects Ltd.order passed
CC00500000002209302/10/2018Vikram J Oswal & Nitin S Jain vs DSK Worldman Projects Ltdorder passed
CC00500000017791414/12/2022SANJAY VISHNU BADVE vs G. S. ASSOCIATESorder passed
CC00500000019813217/01/2023SANJAY REVALKAR , MRS BAKUL SANJAY REVALKAR REVALKAR vs D S KULKARNIorder passed
CC00500000022837821/03/2023Kanchan Narendrakumar Jain vs G S Associatesorder passed
CC00500000023855927/03/2023RAVINDRA R BELSARE vs DS KULKARNI AND COMPANYorder passed
CC00500000027986418/12/2023Sadhana Nagesh Kumar vs D S Kulkarni and Companyorder passed
CC00500000027986518/12/2023Anuradha Vitthal Kulkarni vs D S Kulkarni and Companyorder passed
CC00500000027986618/12/2023Sumedha Kamalakar Sahasrabudhe vs D S Kulkarni and Companyorder passed
CC1240017321/09/2024DAYALAL DEVICHAND JAIN vs GS ASSOCIATESorder passed
CC1240020023/09/2024Kusum Pukhraj Oswal vs GS ASSOCIATESorder passed

A co-operative housing society is recorded as the complainant (Pradeep Wandrekar Chairman of Sadaphuli A, A1 & B CHS Ltd.), and MahaRERA has passed an order.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2024We took over the project as per the Order of the Hon'ble Authority. Only after the due consents were taken the Order came to be passed.

Location, Land & Connectivity

Located at Varale, Varale, Haveli, Pune, 410507. Per the filed land record, the plot is bounded to the north by S 23, to the south by S 7 Hissa 122, to the east by S7 Hissa 122 and to the west by S 7. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park18 km
Baner–Balewadi belt23 km
Pune Int'l Airport (Lohegaon)30 km
Pune Junction / city centre31 km
Kharadi / EON IT Park34 km
Magarpatta / Hadapsar IT35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

GS Associates is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Talegaon Dabhade

Hillcrest
possession by Oct 2026 · Swapnashilp Buildcon
Greendale ENA
possession by Dec 2026 · M/s. Karpe Construction Company
Indraprasth
possession by Dec 2026 · J V Buildcon
Krishna Mahel
Deregistered by MahaRERA · possession by Dec 2026 · Mahesh Developers Ltd
Panoramaa
possession by Dec 2026 · Kakade Properties
SAI Ganesh
possession by Dec 2026 · Aditya Developers

Major developers building in Talegaon Dabhade

Other RERA-registered projects in Pune

Palaash Valley
possession by Dec 2027 · Good Will Developper
Palash Paradise
possession by Jun 2027 · Prachi Infra
Palash, Viva, Pirangut
possession by Jan 2027 · K Raheja Corp Real Estate Private Limite
Palazzo Phase II
declared completion Mar 2026 · S & M Enterprises
Palladio Balewadi Central Phase 1
possession by Dec 2027 · Vilas Javdekar Eco Housing Private Limit
Palladio Balewadi Central Phase 2
possession by Dec 2028 · Vilas Javdekar Eco Housing Private Limit

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026