MahaRERA Property Intelligence · Pune

Pandurang Residency

P52100014215 · bhosari gaoun · promoter Suresh Pandurang Landge

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP52100014215
Registered on16 Nov 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Suresh Pandurang Landge is the promoter of record on 71 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Pandurang Residency1G+430 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at bhosari gaoun , Landge ali , Haveli, Pune, 411026. Per the filed land record, the plot is bounded to the north by 24 M WIDE ROAD, to the south by PLOT NO 87-4-E, to the east by PLOT NO 87-4-A and to the west by PLOT NO 87-4-C. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~96 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park96 km
Baner–Balewadi belt102 km
Pune Int'l Airport (Lohegaon)110 km
Pune Junction / city centre111 km
Kharadi / EON IT Park114 km
Magarpatta / Hadapsar IT116 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhosari

Shrikisan Enclave
possession by Jul 2026 · M/s. Tirupathi Properties Through Prop M
Ellora Shopee
possession by Sep 2026 · Ellora Realities Private Limited
Atlantis
possession by Dec 2027 · Atharva Buildwell
Santiago Skyworld
possession by Jun 2028 · Santiago Realtech
TEN BKC
possession by Dec 2029 · Mahalaxmi Land Developers
Mahadeo Dreams
declared completion May 2026 · Shree Ganesh Associates

Other RERA-registered projects in Pune

Pandurang Residency
possession by Mar 2028 · Shri Mangalmurti Builders And Developers
Pankaj Aasmaan Phase I
declared completion Dec 2019 · Pankaj Developers
Pankaj Aasmaan Phase II
declared completion Mar 2026 · Pankaj Developers
Pankaj Aasmaan Phase III
possession by Dec 2026 · Pankaj Developers
Pankaj Aasmaan Phase IV
possession by Dec 2027 · Pankaj Developers
Pankaj Aasmaan Phase V
possession by Dec 2026 · Pankaj Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026